Section 7 Electrical systems
Clasification Society 2024 - Version 9.40
Clasifications Register Rules and Regulations - Rules and Regulations for the Classification of Naval Ships, January 2023 - Volume 2 Machinery and Engineering Systems - Part 4 Propulsion Devices - Chapter 3 Thrusters - Section 7 Electrical systems

Section 7 Electrical systems

7.1 General

7.1.1 The electrical installation is to be designed, constructed and installed in accordance with the requirements of Vol 2, Pt 4, Ch 3, 7.2 General arrangements.

7.1.2 Where the thruster units are electrically driven, the relevant requirements, including surveys, of Vol 2, Pt 9 Electrotechnical Systems are to be complied with.

7.2 General arrangements

7.2.1 Where a central power generation system is employed, the requirements of Vol 2, Pt 4, Ch 5, 4.3 Power requirements 4.3.5 are to be complied with.

7.2.2 For azimuth thrusters, the generating and distribution system is to be so arranged that after any single failure, steering capability can be maintained or regained within a period not exceeding 45 seconds, and the effectiveness of the steering after such a fault will not be reduced by more than 50 per cent. This may be achieved by the parallel operation of two or more generating sets, or alternatively when the electrical requirements may be met by one generating set in operation, on loss of power, the automatic starting and connecting to the switchboard of a standby set, provided that this set can restart and run a thruster with its auxiliaries.

7.2.3 The failure of one thruster unit or its control system is not to render any other thruster inoperative.

7.3 Distribution arrangements

7.3.1 Azimuth thruster auxiliaries and controls are to be served by individual circuits. Services that are duplicated are to be separated throughout their length as widely as is practicable and without the use of common feeders, transformers, converters, protective devices or control circuits.

7.4 Auxiliary supplies

7.4.1 Where the auxiliary services and thruster units are supplied from a common source, the following requirements are to be complied with:

  1. the voltage regulation and current sharing requirements defined in Vol 2, Pt 9, Ch 2, 6.4 Generator control 6.4.2 and Vol 2, Pt 9, Ch 2, 6.4 Generator control 6.4.7 are to be maintained over the full range of power factors that may occur in services;

  2. auxiliary equipment and services are to operate with any waveform distortion introduced by converters without deleterious effect. (This may be achieved by the provision of suitably filtered/converted supplies).


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.