Section
8 Ships for liquefied gases under pressure and/or partially refrigerated
8.1 Annual Surveys
8.2 Intermediate Surveys – General
requirements
8.2.1 Cargo liquid
level indicating devices are to be generally examined. The low level,
high level and overfill alarms are to be examined and tested to ascertain
that they are in working order. Consideration will be given to the
acceptance of simulated tests provided that they are carried out at
the cargo temperature and/or pressure.
8.2.2 Where applicable,
gas leakage systems are to be examined and tested to ascertain that
they are in working order and calibrated using sample gas.
8.2.3 Where applicable,
the correct functioning of the cargo containment system temperature
indicating equipment, together with any associated alarms, is to be
verified.
8.2.4 Where applicable,
the ventilation system for the spaces surrounding the cargo tanks
and in working spaces is to be examined and checked for satisfactory
operation.
8.2.5 Where applicable,
inert gas systems for the environmental control of cargo tanks and/or
spaces surrounding the cargo tanks are to be generally examined.
8.2.6 Where applicable,
control devices for the cargo containment system and cargo handling
equipment, together with any associated shut-down and/or interlock,
are to be checked under simulated working conditions, and if required,
recalibrated.
8.2.7 The arrangements
for manually operated emergency shut-down are to be checked to ascertain
they are in working order.
8.2.8 Cargo pipelines,
valves and fittings are to be generally examined, with special reference
to expansion bellows, supports and vapour seals on insulated pipes.
8.2.9 Portable
and/or fixed drip trays, or insulation for deck protection in the
event of cargo leakage are to be examined for their condition.
8.3 Intermediate Surveys – Refrigerating equipment
8.3.1 Where refrigerating
equipment for cargo temperature and pressure control is fitted the
following are to be examined so far as practicable:
-
The machinery under working conditions.
-
Shells of all pressure
vessels in the system including primary refrigerant gas and liquid
pipes, cargo vapour and liquid condensate pipes and condenser cooling
arrangements. Insulation need not be removed, but any deterioration
or evidence of dampness is to be investigated.
8.4 Special Surveys – General requirements
8.4.2 All cargo tanks are to be examined internally and externally so far as
practicable, particular attention being paid to the plating in way of supports and of
chocking and securing arrangements and pipe connections.
8.4.3 Where cargo
tanks are insulated and the insulation accessible, the insulation
should be examined externally and sections removed for examination
of the tank if considered necessary by the Surveyor.
8.4.4 The Surveyor may require to gauge, by ultrasonic thickness measurement or
other approved means, the thickness of the material in any portion of the cargo tank
structure where sign of wastage is evident, wastage is normally found or where there is
doubt as to the condition of the structure in way of insulation. Any parts of the cargo
tank structure which are found defective or materially reduced in scantlings are to be
made good by materials of approved scantlings and quality.
8.4.5 Cargo tank
internal pipes and fittings are to be examined, and all valves and
cocks in direct communication with the interiors of tanks are to be
opened out for inspection and connection pipes are to be examined
internally, so far as practicable.
8.4.6 Pressure
relief valves and vacuum relief valves are to be opened out for inspection
and are to be adjusted afterwards. Valves may be removed from tanks,
cargo gas and liquid pipelines for this purpose.
8.4.7 All cargo
pumps, cargo booster pumps and cargo vapour pumps, where applicable,
are to be opened out for examination.
8.4.8 Where considered
necessary by the Surveyor, insulated cargo gas and liquid pipelines
are to have sections of insulation removed to ascertain the condition
of the pipes.
8.4.9 Where equipment
for the production of inert gas is fitted, it is to be examined and
tested to show it to be operating satisfactorily within the gas specification
limits. Pipelines, valves, etc. for the distribution of the inert
gas are to be generally examined. Pressure vessels for the storage
of inert gas are to be examined internally together with their fastenings.
Pressure relief valves are to be demonstrated to be in good working
order. Liquid nitrogen storage vessels are to be examined as far as
practicable and all control equipment, alarms and safety devices are
to be verified as operational.
8.5 Special Surveys – Refrigerating equipment
8.5.1 Each reciprocating
compressor is to be opened out. Cylinder bores, pistons, piston rods,
connecting rods, valves and seats, glands, relief devices, suction
filters and lubricating arrangements are to be examined. Crankshafts
are to be examined but crankcase glands and the lower half of main
bearings need not be exposed if the Surveyor is satisfied with the
alignment and wear.
8.5.2 Where other
than reciprocating type compressors are fitted, or where there is
a program of replacement instead of surveys on board, alternative
survey arrangements will be considered. Each case will be given individual
consideration.
8.5.3 The water
end covers of condensers are to be removed for examination of the
tubes, tubeplates and covers.
8.5.4 Refrigerant
condenser cooling water pumps, including standby pump(s) which may
be used on other services, are to be opened out for examination.
8.5.5 Where a
pressure vessel is insulated, sufficient insulation is to be removed,
especially in way of connections and supports, to enable the vessel’s
condition to be ascertained.
8.5.6 Insulated
pipes are to have sufficient insulation removed to enable their condition
to be ascertained. Vapour seals are to be specially examined for condition.
8.5.7 The Surveyor
is to satisfy himself that all pressure relief valves and/or safety
discs throughout the system are in good order. No attempt, however,
is to be made to test primary refrigerant pressure relief valves on
board ship.
8.6 Special Surveys of ships over 10 years old
8.6.2 All pressure
vessels of inert gas installations are to be examined internally and
externally and tested.
8.6.3 Cargo tanks
are to be pressure tested to a pressure of 1,25 times the working
pressure.
8.7 Thickness measurement of tank
plating
8.7.1 In addition to the requirements of Pt 1, Ch 3, 8.4 Special Surveys – General requirements 8.4.4, thickness measurement of cargo tank plating is to be
carried out at each Special Survey by ultrasonic thickness measurement or other approved
means, to determine the amount of any general diminution. The gauging is to be carried
out in at least two places of the bottom, forward and aft tank plating, side and top
plating. The remainder of the plating is to be gauged as deemed necessary by the
Surveyor, taking into account the results of gauging already carried out.
|