Section
7 Inspection, workmanship and testing procedures
7.1 General
7.2 Construction standards
7.2.1 Construction
standards for all materials are to be in accordance with National
Standards or these Rules whichever are the higher.
7.3 Testing procedures
7.3.1
Definitions. For the purpose of these procedures the following definitions
apply:
-
Protective
coating is the coating system applied to protect the structure
from corrosion. This excludes the prefabrication primer.
-
Structural
testing is a hydrostatic test carried out to demonstrate the
tightness of the tanks and the structural adequacy of the design.
Where practical limitations prevail and hydrostatic testing is not
feasible, hydropneumatic testing, see (e), may be carried
out instead.
-
Leak testing is
an air or other medium test carried out to demonstrate the tightness
of the structure.
-
Hose testing is
carried out to demonstrate the tightness of structural items not subjected
to hydrostatic or leak testing, and other components which contribute
to the watertight or weathertight integrity of the hull.
-
Hydropneumatic
testing is a combination of hydrostatic and air testing, consisting
of filling the tank with water and applying an additional air pressure.
The conditions are to simulate, as far as practicable, the actual
loading of the tank and in no case is the air pressure to be less
than given in Pt 3, Ch 1, 7.3 Testing procedures 7.3.4.
7.3.2
Application. The testing requirements for tanks, including independent
tanks, watertight and weathertight compartments, are listed in Table 1.7.1 Testing requirements. Tests are to be carried
out in the presence of the Surveyor at a stage sufficiently close
to completion such that the strength and tightness are not subsequently
impaired.
7.3.3
Structural
testing. The attachment of fittings to oiltight surfaces is
to be completed before tanks are structurally tested. Where it is
intended to carry out structural tests after the protective coating
has been applied welds are generally to be leak tested prior to the
coating application.
For welds other than manual and automatic erection welds, manual
fillet welds on tank boundaries and manual penetration welds, the
leak test may be waived provided that careful visual inspection is
carried out, to the satisfaction of the Surveyor, before the coating
is applied. The cause of any discolouration or disturbance of the
coating is to be ascertained, and any deficiencies repaired.
7.3.4
Leak
testing. This is carried out by applying an efficient indicating
liquid (e.g. soapy water solution) to the weld or outfitting penetration
being tested, while the tank or compartment is subject to an air pressure
of at least 0,15 bar (0,15 kgf/cm2).
It is recommended that the air pressure be raised to 0,2 bar
(0,2 kgf/cm2) and kept at this level for about one hour
to reach a stabilised state, with a minimum number of personnel in
the vicinity, and then lowered to the test pressure prior to inspection.
A U-tube filled with water to a height corresponding to the test pressure
is to be fitted for verification and to avoid overpressure. The U-tube
is to have a cross-section larger than that of the air supply pipe.
In addition, the test pressure is to be verified by means of a pressure
gauge, or alternative equivalent system.
For tanks constructed
of steel or aluminium, leak testing is to be carried out, prior to
the application of a protective coating, on all fillet welds and erection
welds on tank boundaries, excepting welds made by automatic processes
and on all outfitting penetrations.
Selected locations
of automatic erection welds and pre-erection manual or automatic welds
may also be required to be tested before coating, at the discretion
of the Surveyor, taking account of the quality control procedures
of the shipyard. Where exempt from this requirement, leak testing
may be carried out after the protective coating has been applied,
provided that the welds have been carefully inspected to the satisfaction
of the Surveyor.
Table 1.7.1 Testing requirements
Item to
be tested
|
Testing
procedure
|
Testing
requirement
|
Double bottom
tanks
|
Structural(1)
|
The greater of:
|
- head of water up to the top of the
overflow
|
- head of water up to the margin
line
|
- head of water representing the
maximum pressure experienced in service
|
Cofferdams
|
Structural(1)
|
The greater of:
|
Forepeak and aft peak
used as tank(3)
|
Structural
|
- head of water up to the top of the
overflow
|
- 1,8m head of water above the
highest point of tank(4)
|
Tank bulkheads
|
Structural(1)
|
The greater of:
|
Deep tanks
|
Structural(1)
|
- head of water up to the top of the
overflow
|
Scupper and discharge pipes in way of
tanks
|
Structural(1)
|
- -1,8m head of water above the highest point of
tank(4)
- - setting pressure of the safety valves, where
relevant
|
Double plate rudders
|
Leak, see Note 5
|
See
Pt 3, Ch 1, 7.3 Testing procedures 7.3.4
|
Watertight doors (below freeboard or
bulkhead deck) and watertight hatches when fitted in place
|
Hose(2)
|
See
Pt 3, Ch 1, 7.3 Testing procedures 7.3.5
|
Watertight doors (below freeboard or
bulkhead deck) when fitted in place
|
Hose(6)
|
Weathertight hatch covers and closing
appliances
|
Hose(8)
|
Fore peak not used as tank
|
Hose(2)
|
Shell doors when fitted in
place
|
Hose(7)
|
Chain locker
|
Structural(9)
|
The greater of:
- head of water up to the top of the spurling pipe
- head of water up to the exposed weather
deck(9)
|
Separate fuel oil tanks
|
Structural
|
Head of water representing the maximum
pressure which could be experienced in service, but not less than
3,5m
|
After peak not used as tank
|
Leak
|
See
Pt 3, Ch 1, 7.3 Testing procedures 7.3.4
|
Note
2. When hose testing cannot be performed
without damaging possible outfittings already installed, it may be
replaced by a careful visual inspection of all the crossings and
welded joints. Where necessary, dye penetrant test or ultrasonic leak
test may be required.
Note
3. Testing of the aft peak is to be
carried out after the sterntube has been fitted.
Note
4. The highest point of the tank is
generally to exclude hatchways. In holds for liquid cargo or ballast
with large hatch openings, the highest point of the tank is to be
taken to the top of the hatch.
Note
5. If leak or hydropneumatic testing is
carried out, arrangements are to be made to ensure that no pressure in
excess of 0,30 bar (0,30 kgf/cm2) can be applied.
Note
7. For shell doors providing watertight
closure, watertightness is to be demonstrated through prototype
testing of the seal system before installation. The testing procedure
is to be agreed with LR.
Note
8. On yachts, as defined in Chapter 1, a
minor seepage of water up to 0,5 litres within 3 minutes, through the
door, is permissible. Weathertight hatch covers and closing appliances
to be tested are those on the weatherdeck in the forward 0,25L
R and those specified in Pt 3, Ch 4, 6.5 Companionways, doors and accesses on weather decks 6.5.2.(b) and Pt 3, Ch 4, 6.5 Companionways, doors and accesses on weather decks 6.5.2.(c) of the Rules for Special Service
Craft.
Note
9. For yachts up to 500GT, the chain
locker arrangement fitted forward of the collision bulkhead may be
accepted, based on the structural plans and leak testing.
|
7.3.5
Hose
testing. This is to be carried out at a maximum distance of
1,5 m with a hose pressure not less than 2,0 bar (2,0 kgf /cm2).
The nozzle diameter is not to be less than 12 mm. The jet is to be
targeted directly onto the weld or seal being tested.
7.3.8 Structural
testing may be carried out afloat where testing using water is undesirable
in dry-dock or on the building berth. The testing afloat is to be
carried out by separately filling each tank and cofferdam to the test
head given in Table 1.7.1 Testing requirements. Alternate
tanks and cofferdams may be filled to the test head and the bottom
and lower side shell in the intermediate empty tanks and cofferdams
and all boundaries are to be examined and the remainder of the bottom
and lower side shell and boundaries examined when the water is transferred
to the remaining tanks.
7.3.9 Where permitted
by Table 1.7.1 Testing requirements, complete structural
testing may be replaced by a combination of leak and structural testing,
as follows. The leak test is generally to be carried out on each tank
while the craft is in dry-dock or on the building berth.
-
Double bottom tanks
and cofferdams may be leak tested on the berth, and structural tests
carried out afloat.
-
All deep tanks are
to be structurally tested. However, where a number of similar tanks
is involved, one typical tank is to be structurally tested and for
the remaining tanks the Surveyor may, at his discretion, permit leak
testing in lieu of structural testing.
-
Interconnecting deep
and double bottom tanks and "flume" type stabilisation tanks are to
be structurally tested to the test head given in Table 1.7.1 Testing requirements.
7.3.10 Equivalent
proposals for testing will be considered.
7.3.11
Trial
trip and operational tests. The items listed in Table 1.7.2 Trial trip and operational
tests are to be tested on completion
of the installation or at sea trials.
Table 1.7.2 Trial trip and operational
tests
Item
|
Requirement
|
Sliding watertight doors
|
To be operated under working
conditions.
|
Windlass
|
An anchoring test is to be carried
out in the presence of the Surveyor. The test is to demonstrate that the
windlass with brakes etc. functions satisfactorily and that the power to
raise the anchor can be developed and satisfies the Rule requirements. For
Rule requirements, see
Pt 3, Ch 5, 8 Anchor windlass design and testing.
|
Steering gear, main and
auxiliary
|
To be tested under working
conditions, to the satisfaction of the Surveyors, to demonstrate that the
Rule requirements are met. For Rule requirements, see
Pt 14, Ch 1 Steering Systems.
|
Davits and deck cranes
|
To be tested under working conditions
to proof load to the satisfaction of the Surveyors.
|
Fire flaps
|
To be operated under working
conditions to the satisfaction of the Surveyors.
|
Means of escape
|
Alternative means of escape from
machinery and accommodation spaces is to be proven to the satisfaction of
the Surveyors. For Rule requirements, see
Pt 3, Ch 2, 4.10 Means of escape.
|
|