Section
2 Construction tolerances
2.1 General
2.1.1 Construction
tolerances are to comply with Pt 3, Ch 1 General Regulations of
the Rules for Special Service Craft. The additional guidance given
in this Chapter should also be complied with where practicable.
2.2 Defects in steel/aluminium products
2.2.2 If lamination
is found during plate preparation the extent of the lamination should
be ascertained by ultrasonic examination. Renewal of the affected
material is normally recommended.
2.3 Construction standards
2.3.1 Construction
standards (including preparation of material, joint alignment, type
of welded joint, fit-up prior to welding, steps to be taken for rectification
of defects, etc.) are to be agreed between LR and the Builder. Such
standards will be recorded and kept on file by LR. In a number of
countries national standards exist in respect of the acceptable shipbuilding
standards.
2.3.2 In shipyards
certified under the LR Quality Assurance Scheme, the standards will
have received general approval as part of the certification procedures
and their application to particular craft will be included in the
quality plan submitted to LR for approval.
2.3.3 In considering critical locations and their construction standards it also
has to be borne in mind that craft construction is a traditional process with alignment
standards based on heel lines. In addition, therefore, to establishing the more critical
joints in terms of fatigue life, consideration of the thicknesses to be employed in
these joints should be a fundamental factor. If the heel line principle is maintained at
the toes of, for example, primary member end brackets, where increased thicknesses are
employed, the arrangements will in reality, be out of line, even though perfect
alignment is attained to the standard, see
Figure 3.2.1 Recommended alignment of primary members. It is therefore recommended, particularly
for aluminium, that a median line principle is employed at this local area so that an
improved alignment can be more easily attained. From LR's point of view the various
thicknesses of plating at structural joints, particularly the higher stress joints, is
an important consideration. In this respect the gradient of load through the through
thickness loaded plate should be controlled to a maximum of one in three, see
Figure 3.2.1 Recommended alignment of primary members.
2.4 Prefabrication
2.4.1 Throughout
the preparation of material and assembly of prefabrication units,
the workmanship is to be inspected in order to ensure that correct
procedures are being followed. By attention in the early stages of
construction, undesirable procedures and faulty workmanship can be
avoided, or their consequences minimised. When the existence of such
defects is noticed prompt and suitable measures are to be taken for
rectification.
2.4.2 Examination
of structure will normally be carried out during the prefabrication
of units, and liaison between the LR Surveyor and the Builder's drawing
offices and quality control departments will ensure that attention
is also given to details which may not have been included on approved
plans (air and drainage holes, etc.) during early material preparation
stages.
Figure 3.2.1 Recommended alignment of primary members
2.4.3 It should
be borne in mind that visual examination of welds and plating of a
finished structure does not necessarily ensure a complete and satisfactory
survey. Procedures are to be such as to ensure that adequate inspection
is made of joint preparation before welding. Attention is drawn to
the guidance on welding and structural details in Pt 6, Ch 2 Construction Procedures and Pt 7, Ch 2 Construction Procedures of
the Rules for Special Service Craft for steel and aluminium alloy
craft respectively. Regular examination by the LR Surveyor, in conjunction
with the Builder, of non-destructive examination and other Quality
records provides a check on the quality of welding operations and
any decline in standards should be investigated, including additional
tests as considered desirable.
2.4.4 It is
essential that a good standard of cleaning be achieved for these inspections.
Special attention, as indicated in Ch 13, 1.7 Assembly and preparation for welding 1.7.8 of the Rules for Materials, are to be applied for
aluminium. For steel structures welding slag should be removed and
rusting of weld deposits should be removed by wire brushing.
2.5 Assembly of units
2.5.1 The Builder
and the LR Surveyors must ensure by regular and systematic examination
that the control exercised up to the stage of block assembly is maintained
by the efficient erection of blocks at the berth. It is particularly
necessary at this point to ensure that fit-up, alignment, adjustment
and welding of blocks is in accordance with the approved plans and
building standards. Attention is to be given to the sequence of erection
and of welding. Particular attention should be given to length allowance
for unwelded stiffening member alignment.
2.5.2 With
the assembly of large blocks careful attention should be paid to the
areas in way of lifting lugs. It is not unusual to find small cracks
in the vicinity of the weld area after removal of lugs. Where lugs
are removed the dressing of the plate must be thorough and examination
by means of crack detection of the finished surface is good practice.
Repair of any cracks found must be carried out by skilled welders
under strict control.
Figure 3.2.2 Recommended alignment of secondary stiffening members
2.5.3 Any unusual
incidents during construction, such as fracturing of plates, should
be noted and brought to the attention of the LR Surveyor. It will
be necessary to have full information on the circumstances affecting
such cases, such as position and extent of the fracture relative to
adjacent structure and welds, atmospheric temperature, details of
joints, precise stage and sequence of welding, type of electrode filler
wire used, whether or not pre-heating was used, grades of steel or
aluminium alloy involved and any other factors considered to have
had a possible influence. Test details of affected plates and proposals
for remedial measures should also be made available. Where doubt exists
in establishing the source of such incidents, the assistance of LR's
staff at Headquarters, should be sought.
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
 |
|