Section
14 Machinery planned maintenance and condition monitoring, MPMS,
MCM and RCM
14.1 Introduction
14.1.2 Planned
maintenance systems may be based on calendar or running hours calling
for items to be opened out for inspection and overhaul at specified
periods. Alternatively the machinery may be monitored for condition
and performance, whereby items need only be opened out for examination
when readings indicate deterioration.
14.1.3 Navies
who operate a planned maintenance scheme that meets the LR requirements
will benefit from enhanced arrangements for dealing with machinery
surveys. The arrangements provide the following advantages:
-
A more flexible
approach to dealing with Classification Surveys of machinery items.
The condition as observed and reported by an LR approved Marine Engineer
Officer will, subject to annual audit, be sufficient to credit the
items for survey.
-
A single system
can be operated by the Navy covering maintenance, spare parts' supply
and survey requirements.
-
The schemes allow
the application of condition monitoring techniques to main and auxiliary
items of machinery.
14.1.4 When
a Navy decides to apply such arrangements to limit the opening out
normally required for survey under CSM then MPMS,
MCM (including Condition Monitoring) or RCM (including
Reliability Centred Maintenance) class notations can be assigned where
the schemes have been approved by LR.
14.2 Master list items
14.2.1 A list of typical machinery master list items that can be surveyed by
authorised personnel and those items that remain to be dealt with by LR Surveyors can be
obtained from LR’s Southampton GTC Office. It should be noted that LR will continue to
inspect, as necessary, where there is a history of mechanical, electrical or control
engineering defects in a particular area, either on the ship or on a similar ship.
14.3 The planned maintenance approach
14.3.1 Types
of maintenance are defined as:
-
Preventive
maintenance. This calls for items to be opened out for inspection
and overhaul at specified time periods or after a specified number
of running hours in order to keep the machine/equipment/system in
a satisfactory operational condition.
-
Condition
based maintenance. This is dictated by the performance or physical
state of the machine/equipment/ system, determined by regular or continuous
checks of applicable parameters. Maintenance is only undertaken when
conditions have approached or reached the lowest acceptable standard
and before breakdown or failure occurs.
-
Reliability
centred maintenance. This calls for a structured analysis of
a system's capability to perform its functions from design through
operation to decommissioning. The primary objective is to ensure the
functionality of a system and this is achieved through a planned maintenance
strategy determined from the detailed analysis. The strategy may include
the use of prevention and condition based maintenance.
14.3.2 The
types of maintenance described in Vol 1, Pt 1, Ch 3, 14.3 The planned maintenance approach 14.3.1 are the foundations of a Machinery Planned Maintenence System
acceptable to LR. Many schemes are made up with a combination of the
three methods of control. In addition, to deal with unforeseen circumstances,
any Machinery Planned Maintenence System must also be able to deal
effectively with breakdown or corrective maintenance, i.e. unscheduled
maintenance.
14.4 Basic requirements for approval of MPMS, MCM and RCM schemes
14.4.1 To obtain approval of a MPMS, the Navy is required to make a formal
request through either a local office of LR or direct to LR in the Southampton GTC
office. The request is to be accompanied by the following information:
-
A numbered index
of the items to be included in the scheme. This index is to include
at least all CSM items that appear on the Master List
of Surveyable Items. The scheme can also cover many items that are
not required for classification. The indexing system is to be such
that ready cross-reference to the numbers in the LR Master List of
Surveyable items can be made. It is also to indicate those items to
be dealt with by preventive maintenance, by condition-based maintenance
and by reliability centred maintenance.
-
The maintenance
and monitoring methods to be used, the time schedules for each item
and limits of acceptance/ condition where applicable. Maintenance
descriptions are to cover at least the minimum opening out necessary
to demonstrate that a satisfactory examination of the item will be
made. The extent of the work to be undertaken is to be indicated but
it is not necessary for approval purposes to include every detailed
job description. A few sample job descriptions will suffice to demonstrate
how the system works. Machinery on preventive maintenance must be
examined completely for survey purposes at intervals not exceeding
six years, although in practice many items will be maintained much
more frequently.
-
A system for
reporting to the Navy and recording on board ship and at the Navy's
headquarters, details of maintenance carried out, the condition as
found and any repairs effected, together with a list of spare parts
used. The reporting and recording procedures are to be sufficiently
comprehensive to demonstrate that both the Navy and the LR Surveyor
can verify correct operation of the planned maintenance system at
the time of the survey.
-
A description
of the scheme regarding its application on board ship and the proposed
flow of maintenance documents and method of filing same. The application
of the scheme may take the form of simple planning charts or the more
complex interactive computer based systems. The language of the MPMS is to be English.
14.4.3 The
following information is to be submitted to LR for review:
-
Hard or soft
copy (with operating systems if necessary) of the studies, conducted
in accordance with a relevant national or international Standard,
such as ISO 17359, Condition monitoring and diagnostics of machines
– General guidelines. This is to include, operating context,
details of study team, Risk Assessment (RA, see also
Vol 2, Pt 1, Ch 3, 18 Risk Assessment (RA)), algorithm decision
sheets, summary of maintenance tasks, summary of ’level of repair
analysis’, identification of ’critical’ spares.
-
Details of system/equipment
covered by the study.
-
Confirmation
that maintenance studies have included where possible, OEM data on
failure rates, OEM maintenance recommendations, and associated information
necessary to ensure that risk associated with component failure is
accounted for accurately.
14.4.4 LR
will verify by audit that the following items have been complied with:
-
Study has been
undertaken in full compliance of the methodology embodied in an acceptable
and applicable standard for RCM.
-
Study team members
have adequate experience both of undertaking RCM studies
and the systems/equipment under review.
-
Study team members
have been present during the study for sufficient time (percentage
of total time taken) to contribute properly to the study.
-
No 'Mandatory
Redesign' requirements are outstanding.
-
Where spares
have been identified as 'Critical', they have been properly identified
in the management systems on board.
-
Procedures for
collection of condition monitoring information have been established
and reporting procedures for submission of this as part of the approved MPMS are clearly documented.
-
Where Standard
Operating Procedures have been identified, that an adequate management
system is in place to ensure that they are complied with.
-
The RA, see
Vol 2, Pt 1, Ch 3, 18 Risk Assessment (RA),
is in compliance with an acceptable standard, good marine engineering
practice and application of valid reliability data.
14.4.5 A
technical audit by LR of individual RCM studies selected by LR will
follow the following methodology:
-
Verification
that the study covers the entire function being addressed.
-
For each individual
study (sub function) within a group function, verification that there
is a list that includes the individual assets items, including controls,
instrumentation and protective/ emergency devices.
-
Verification
that an expected maintenance task list has been drafted, based on
typical tasks that would be expected for the relevant item, under
any maintenance regime. These would include, but may not be limited
to, system performance analysis checks, standard condition monitoring
checks (vibration, electrical characteristics, thermography, etc),
inspections of items liable to wear or other age related degradation,
i.e. fouling, periodic tests of protective devices, operation of reversionary
modes of operation, etc.
-
Confirm that
the standard tasks have been identified for each sub function.
-
Review the study
for justification for items or systems with no scheduled maintenance
for tasks not identified.
-
Review any inconsistencies
in periodicity for tasks included in maintenance schedule.
-
Carry out a review
of RCM logic applied for one sub function. If the review
is acceptable and in accordance with the standard for RCM, others
will not be fully reviewed. If considered unacceptable, a review of
another will be carried out for confirmation. If second also unacceptable,
LR will require a complete review of all other sub functions for acceptance.
-
Review LR Master
List Surveyable items to verify that all Class items have a maintenance
programme associated with credit as part of RCM.
14.4.6 As
an alternative to LR carrying out post study audits required by Vol 1, Pt 1, Ch 3, 14.4 Basic requirements for approval of MPMS, MCM and RCM schemes 14.4.4 and Vol 1, Pt 1, Ch 3, 14.4 Basic requirements for approval of MPMS, MCM and RCM schemes 14.4.5, LR can, if requested, provide
direct input and advice to the study team(s) on either a full or part
time basis to supplement the technical/survey requirement input. If
this is undertaken, the scope of the audit will be reduced accordingly.
14.4.7 Where
machinery items are maintained on a condition basis the following
additional information is required to be submitted:
-
A description
of the applicable monitoring techniques and monitoring equipment to
be used.
-
A statement as
to the acceptable limits of deteriorated condition. These should be
derived from the manufacturer's recommendations, applicable severity
criteria as defined in recognised Standards, or the Navy's required
limits when these are more severe. Rotating machinery on condition
based maintenance may be accepted for survey on the basis of the monitored
readings without opening out if the condition is shown to be good.
14.4.8 If
the planned maintenance scheme is considered to be acceptable to LR
a ‘Certificate for Operation of an Approved Planned Maintenance
Scheme’ will be issued. The Certificate is to be retained on
board the subject ship for the information of the Commanding Officer,
Marine Engineer Officer and LR's Surveyors.
14.4.9 The
Marine Engineer Officer operating the Scheme on a ship must hold a
valid LR Certificate of Authorisation.
14.5 Conditions of operation
14.5.1 It
is a condition of the Scheme that the Navy arranges for LR Surveyors
to carry out an Annual audit of the machinery maintenance and monitoring
records. Annual audits are to be held within three months before or
after the due date and it is recommended that they are harmonised
with the ship's Annual Survey.
14.5.2 Marine
Engineer Officers may carry out surveys of all the machinery items
for which they are authorised, at sea or in port, whichever is the
most convenient. The following machinery items remain to be dealt
with by an LR Surveyor, unless special arrangements have been agreed
with the Navy:
- Machinery damage, repairs and alterations, see
Vol 1, Pt 1, Ch 3, 14.6 Breakdown or corrective maintenance
- Gas turbines for propulsion and electrical supplies.
- Engines for propulsion and electrical supplies.
- Steam turbines and boilers for propulsion and electrical supplies.
- Control, alarm and safety devices associated with the above main
and auxiliary machinery.
- Reduction/increase gearing, flexible couplings and clutches.
- Holding down bolts and chocks.
- Steam pipes and valves on ships with steam turbine installations.
- Air receivers and other pressure vessels.
- Starting air pipes.
- Steering machinery.
- Pumping arrangements for bilge and dewatering systems.
- Electrical equipment other than auxiliary motors.
- Screwshafts, stern bearings and propellers.
- Sea connections.
- Machinery controls and controls associated with Class Notations,
e.g. UMS, CCS, ICC and IP.
- Engine Trial.
- First start arrangement trial.
14.5.3 The
confirmatory survey carried out at the time of the annual audit by
LR's Surveyor will comprise of checks of the condition monitoring
records and, if considered necessary, an examination of selected main
and auxiliary machinery under working conditions.
14.6 Breakdown or corrective maintenance
14.6.1 LR
is required to be notified when a breakdown or defect occurs and has
a major effect that affects the Provisions of Classification and repairs
are necessary. A major effect is an effect that produces:
-
a significant
increase in the operational duties of the crew or in their difficulty
in performing their duties which by itself should not be outside the
capability of a competent crew provided that another major effect
does not occur at the same time; or
-
significant degradation
in the operational capability of the ship; or
-
significant modification
of the permissible operating conditions, but will not remove the capability
to complete a safe journey without demanding more than normal skill
on the part of the operating crew.
14.6.2 In
discussion with the Navy and the Marine Engineer Officer, LR will
advise what repairs and/or renewals are necessary for classification
purposes, with the issue of an Interim Certificate of Class.
14.6.3 The
required repair and time scale for completion will be the subject
of discussion and agreement with LR and the Navy. It is the responsibility
of the Navy to decide whether the ship's mission/operational tasking
is more important than completing the repairs within the agreed time.
It is accepted that such circumstances are occasionally inevitable,
and LR would provide advice on the interim measures that could be
introduced until such time as the required repairs are carried out
and the implications on a ship's operating capability of delays in
effecting repairs.
14.7 Annual audit and survey
14.7.1 At
the annual audit the Marine Engineer Officer is required to make available
the maintenance and monitoring records. These records may be in a
hard or soft format and should include:
-
Appropriate records
of machinery or equipment surveyed under the supervision of the Marine
Engineer Officer that are listed in the Master List of Surveyable
Items. These statements should give details of repairs carried out
and spare parts used.
-
Written details
of any breakdown or malfunction of essential machinery. Such details
should include the main cause of failure.
These records will be examined in sufficient depth by the LR
Surveyors to ensure that the scheme has been correctly operated and
that the machinery has functioned satisfactorily since the previous
survey. The records should indicate that all scheduled maintenance
has been carried out. Any items not dealt with as per schedule will
be discussed with the Marine Engineer Officer.
14.7.2 Where
condition monitoring of main or auxiliary machinery is incorporated
in the PMS the LR Surveyor will examine the records to verify that
vibration levels, performance criteria, etc. are within the approved
specified limits. The LR Surveyor may require confirmatory readings
on available running machinery to be taken for comparison with the
ship's records.
14.7.3 As
part of the audit, LR Surveyors carry out a general examination of
the machinery. As far as is practicable machinery to be credited for
survey will be examined under working conditions. If the LR Surveyor
is not satisfied with the condition as found he might require to have
any items opened out for inspection.
14.7.4 The
dates of items to be credited for Class will be aligned to the date
of the confirmatory survey regardless of when the Marine Engineer
Officer carried out his survey. Any other surveyable items of machinery
not covered by the Scheme will be surveyed and credited in the normal
way.
14.7.5 For
items which the Marine Engineer Officer is authorised to survey and
become due for survey between Annual Audits these will be shown as
‘OVERDUE' on the survey status until the Annual Audit has been
held and reported.
14.7.6 In
the event of the Surveyor not being satisfied that the planned maintenance
scheme is being correctly followed, either from the maintenance records
or from the general condition of the machinery, a report will be forwarded
to LR recommending that the special arrangements for dealing with
machinery surveys be suspended.
|