Section 2 Repair of pitting
Clasification Society 2024 - Version 9.40
Clasifications Register Guidance Information - Naval Survey Guidance for Steel Ships, January 2001 - Chapter 12 Pitting - Section 2 Repair of pitting

Section 2 Repair of pitting

2.1 General

2.1.1 The welding of internally pitted bottom shell plating may be carried out afloat provided the following additional requirements are complied with:

  1. That the pitting is adequately prepared in respect of shape, cleanliness and dryness.

  2. Such repairs are not permitted in the following circumstances:

    1. Where pitting is closely spaced.

    2. On grade E or EH quality steels, or above.

    3. Where the thickness of the material left at the bottom of the pit is less than 6 mm.

  3. Welding consumables are to be selected from the List of Approved Welding Consumables for use in Ship Construction.

  4. The pits are to be welded in a downhand position, and the selection of correct consumables is to ensure that the appropriate toughness will be achieved under the conditions of accelerated cooling provided by the water on the outside of the shell.

  5. The use of submerged arc welding in this application has not always provided optimal results. Where it is proposed as a repair, guidance should be sought from an appropriate welding specialist.

  6. Whatever process and consumable is used, the heat input must not be less than 1,5 KJ/mm. If, for example, the welding is carried out with a covered electrode as small as 4 mm diameter, then it must be deposited at a controlled rate such that the length of weld run does not exceed the electrode length consumed.

  7. Taking into account the rapid cooling due to the presence of water outside, a random inspection of the first run of the welding, followed by a random inspection of the finished weld, is to be carried out by the Surveyor. These random inspections should be supplemented by NDE methods for the detection or discovery of any cracks.

2.1.2 An alternative to Ch 12, 2.1 General 2.1.1 is to use an external cofferdam fixed by a qualified diving contractor to isolate the pitting from the water.

2.1.3 Full details of the exact nature, location and extent of repairs should be reported and a suitable note should be made in the Memoranda in the case of repairs involving the use of epoxy compound.

2.1.4 The permanent repair of bottom shell pitting by fitting large numbers of welded doubling plates is not acceptable.

2.1.5 Where the pitting occurs in the bottom of a tank forming part of a tank top, the intensity of the pitting should be examined and the Surveyor should consult with the Owner/Naval Authority as to the best method of repair to be carried out in the tank.


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.