Section
4 General requirements for manufacture
4.1 General
4.1.1 The following
definitions are applicable to these Rules:
Item:
|
A single forging, casting, plate,
tube or other rolled product as delivered.
|
Piece:
|
The rolled product from a single slab
or billet or from a single ingot if this is rolled directly into plates,
strip, sections or bars.
|
Batch:
|
A number of similar items or pieces
presented as a group for acceptance testing.
|
Wide Flat:
|
flat product of a width
over 150 mm, up to and including 1250 mm and thickness generally over 4 mm.
Edges are square cut, i.e. hot rolled on the four sides. Supplied in
lengths, not coils.
|
Plate/Sheet:
|
flat rolled product
whereby the edges are allowed to deform freely. Supplied flat and generally
in square or rectangular shapes with a width of 600 mm or over, but other
shapes may also apply.
|
4.1.2 Where a manufacturer
purchases semi-finished products (e.g. slabs) for the purpose of re-processing
(e.g. rolling), the manufacturer is to ensure that the materials are
from an LR approved manufacturer, and manufactured within the scope
of approval of that manufacturer. The aim of chemical analysis, dimensions,
surface and internal quality checks are to be agreed between the manufacturer
and purchaser. The semi-finished materials must be supplied with appropriate
certification, according to these Rules.
4.1.3 It is the
responsibility of the manufacturer to ensure compliance with all relevant
aspects of these Rules. All deviations are to be recorded as non-compliances,
and brought to the attention of the Surveyor, along with corrective
actions taken. Failure to do this is considered to render the material
as not complying with these Rules.
4.1.4 The manufacturer
is to maintain all test and inspection records required by these Rules
for at least seven years. Records are to be made available to LR on
request.
4.1.5 Where material
is produced which does not meet all aspects of these Rules, the manufacturer
may apply to LR for a concession to certify the material as approved.
LR will consider each application on a case-by-case basis, although
concession will only normally be granted in exceptional circumstances.
If the concession is granted, a formal written numbered concession
will be issued to the manufacturer. The concession number must be
applied to the approval certificate, whether it is an LR certificate
or a validated manufacturer's certificate.
4.2 Chemical composition
4.2.1 The ladle
analysis used for certification purposes is to be determined after
all alloying elements have been added and sufficient time allowed
for such additions to equalise throughout the ladle.
4.2.2 The method
of taking samples is to ensure that the reported analysis is representative
of the cast. In addition, the manufacturer must determine and certify
the chemical composition of every heat of material.
4.2.3 Where more
than one sample is taken, the method of averaging for the final certificate
result and the determination of acceptable variations in composition
are to be agreed with the Surveyor.
4.2.4 The chemical
composition of ladle samples is to be determined by the manufacturer
in an adequately equipped and competently staffed laboratory. The
manufacturer's analysis will be accepted, but may be subject to occasional
independent checks if required by the Surveyor.
4.2.5 The analysis
is to include the content of all the elements detailed in the relevant
Sections of the Rules and, where appropriate, the National or International
Standard applied.
4.2.6 At the discretion
of the Surveyors, a check chemical analysis of suitable samples from
products may also be required. These samples are to be taken from
the material used for mechanical tests but, where this is not practicable,
an alternative procedure for obtaining a representative sample is
to be agreed with the manufacturer. For product samples, the permissible
limits of deviation from the specified ladle analysis are to be in
accordance with an appropriate International or National Standard
specification.
4.3 Heat treatment
4.3.1 Materials
are to be supplied in the condition specified in, or permitted by,
the relevant Chapters of these Rules.
4.3.2 Heat treatment is to be carried out in properly constructed furnaces which
are efficiently maintained and have adequate means for control and recording of
temperature. The furnace dimensions are to be such as to allow the whole item to be
uniformly heated to the necessary temperature. In the case of very large components
which require heat treatment, alternative methods will be specially considered. Furnace
temperature uniformity surveys to recognised standards (e.g. ASTM A991/A991M) shall be
carried out at the specified frequency.
4.3.3 The manufacturer
is to maintain the records, including the temperature charts of all
heat treatments for at least seven years.
4.4 Test material
4.4.1 Sufficient
test material is to be provided for the preparation of the test specimen
detailed in the specific requirements. It is, however, in the interests
of manufacturers to provide additional material for any re-tests which
may be necessary, as insufficient or unacceptable test material may
be a cause for rejection.
4.4.2 The test
material is to be representative of the item or batch and is not to
be separated until all the specified heat treatment has been completed,
except where provision for an alternative procedure is made in subsequent
Chapters of these Rules.
4.4.3 All test
material is to be selected by the Surveyor or an authorised deputy
and identified by suitable markings which are to be maintained during
the preparation of the test specimens.
4.5 Mechanical tests
4.5.2 Where Charpy
impact tests are required, a set of three test specimens is to be
prepared and the average energy value is to comply with the requirements
of subsequent Chapters. One individual value may be less than the
required average value provided that it is not less than 70 per cent
of that value.
4.5.3 In the Rules,
mechanical properties are specified in SI units, but alternative units
may be used for acceptance testing. In such cases, the specified values
are to be converted in accordance with the appropriate conversions
given in Table 1.4.1 Conversions from SI units to
metric and Imperial units. It is preferred
that test results be reported in SI units, but alternative units may
be used provided that the test certificate gives, in the same units,
the equivalent specification values.
Table 1.4.1 Conversions from SI units to
metric and Imperial units
1
N/mm2 or MPa
|
=
|
0,102 kgf/mm2
|
1
N/mm2 or MPa
|
=
|
0,0647
tonf/in2
|
1
N/mm2 or MPa
|
=
|
0,145 x 103
lbf/in2
|
1J
|
=
|
0,102 kgf m
|
1J
|
=
|
0,738 ft lbs
|
1
kgf/mm2
|
=
|
9,81 N/mm2 or
MPa
|
1
tonf/in2
|
=
|
15,4 N/mm2 or
MPa
|
1
lbf/in2
|
=
|
6,89 x 10–3
N/mm2 or MPa
|
1 kgf
m
|
=
|
9,81 J
|
1 ft lbf
|
=
|
1,36 J
|
4.6 Re-test procedures
4.7 Rectification of defective material
4.7.1 Small surface
imperfections may be removed by mechanical means provided that, after
such treatment, the dimensions are acceptable, the area is proved
free from defects and the rectification has been completed in accordance
with any applicable requirements of subsequent Chapters of these Rules
and to the satisfaction of the Surveyor.
4.7.2 The repair
of defects by welding can be accepted only when permitted by the appropriate
specific requirements and provided that the agreement of the Surveyor
is obtained before the work is commenced. When a repair has been agreed,
it is necessary in all cases to prove by suitable methods of non-destructive
examination that the defects have been completely removed before welding
is commenced. Welding procedures and inspection on completion of the
repair are to be in accordance with the appropriate specific requirements
and are to be to the satisfaction of the Surveyor.
4.7.3 Manufacturers
wishing to carry out welding work must have at their disposal the
necessary workshops, lifting gear, welding equipment, pre-heating,
and where necessary annealing facilities and testing devices, as well
as certified welders and supervisors to enable them to perform the
work properly. Proof shall be furnished to the Surveyor that these
conditions are satisfied before welding work begins.
4.8 Identification of materials
4.8.1 The manufacturer is to adopt a system of identification which will enable
all finished materials to be traced to the original cast, and the Surveyors are to be
given full facilities for tracing the material when required. When any item has been
identified by the personal mark of a Surveyor, or his deputy, this is not to be removed
until an acceptable new identification mark has been made by a Surveyor. Failure to
comply with this condition will render the item liable to rejection.
4.8.2 Before any item is finally accepted it is to be clearly marked by the
manufacturer in at least one place with the particulars detailed in the appropriate
specific requirements.
4.8.3 Where hard stamps such as the LR brand stamp are issued to manufacturers to
carry out the stamping on behalf of LR, the procedure for issue, maintenance and use of
stamps is to be agreed in writing.
4.8.4 Identification and marking is normally made by hard stamping, however, alternative
methods may be used by prior agreement. Such methods may be an electronic tagging system
such as RFID labels, electric etching, stenciling, or painting. Paints used to identify
alloy steels are to be free from lead, copper, zinc or tin, i.e. the dried film is not
to contain any of these elements in quantities of more than 250 ppm.
4.8.5 Where alternative methods are to be used, the manufacturer shall have in place a
procedure detailing the process and controls for the identification of materials, and
control measures for effective traceability of materials.
4.8.7 Where a number of light identical products, such as sections and bars
weighing ≤ 50 kg per meter, are securely fastened together in bundles, the manufacturer
need only brand each bundle. A durable label giving the required particulars may be
attached to each bundle.
|