Section 5 Specific requirements for pressure piping
Clasification Society 2024 - Version 9.40
Clasifications Register Rules and Regulations - Rules for the Manufacture, Testing and Certification of Materials, July 2022 - Chapter 13 Requirements for Welded Construction - Section 5 Specific requirements for pressure piping

Section 5 Specific requirements for pressure piping

5.1 Scope

5.1.1 Fabrication of piping is to be carried out in accordance with the requirements of this Section and the general requirements given in Ch 13, 1 General welding requirements, unless more stringent requirements have been specified.

5.1.2 Piping systems are to be constructed in accordance with the approved plans and specifications.

5.1.3 Fabricated piping will be accepted only if manufactured by firms that have demonstrated that they have the facilities and equipment and are competent to undertake the quality of welding required for the Class of pipework proposed.

5.2 Manufacture and workmanship

5.2.1 Pipe welding may be performed using manual, semi-automatic or fully automatic electric arc processes. The use of oxy-acetylene welding will be limited to Class 3 piping in carbon steel or carbon/manganese material that is not for carrying flammable fluids and limited to butt joints in pipes not exceeding 100 mm diameter or 9,5 mm thickness.

5.2.2 Welding of piping, including attachment welds directly to pressure retaining parts is to be performed in accordance with approved welding procedures that have been qualified in accordance with Ch 12 Welding Qualifications.

5.2.3 Where the work involves a significant number of branch connections, tests will be required to demonstrate that the type of joint(s) and welding techniques employed are capable of achieving the required quality.

5.2.4 Where pressure piping is assembled and butt welded in situ, the piping is to be arranged well clear of adjacent structures to allow sufficient access for preheating, welding, heat-treatment and non-destructive examination of the joints.

5.2.5 Alignment of pipe butt welds is to be in accordance with Table 13.5.1 Pipe butt weld alignment tolerances unless more stringent requirements have been agreed. Where fusible inserts are used, the alignment is to be within 0,5 mm in all cases.

Table 13.5.1 Pipe butt weld alignment tolerances

Pipe size Maximum permitted misalignment
D < 150 mm and t ≤ 6 mm 1,0 mm or 25% of t, whichever is the lesser
D < 300 mm and t ≤ 9,5 mm 1,5 mm or 25% of t, whichever is the lesser
D ≥ 300 and t > 9,5 mm 2,0 mm or 25% of t, whichever is the lesser
where

D = pipe internal diameter

t = pipe wall thickness

5.2.6 The number of welds is to be kept to a minimum. The minimum separation between welds, measured toe-to-toe, is to be not be less than 75 mm. Where it is not possible to achieve this, adjacent welds are to be subjected to surface crack detection NDE.

5.2.7 Welding consumables and fusible root inserts, where used, are to be suitable for the materials being joined.

5.2.8 Acceptable methods of flange attachment are to be used, see Figure 12.2.2 Typical welded-on flanges in Pt 5, Ch 12 Piping Design Requirementsof the Rules for Ships. Where backing rings are used with flange type (a) they are to fit closely to the bore of the pipe and be removed after welding. The rings are to be made of the same material as the pipes. The use of flange types (b) and (c) with alloy steel pipes is limited to pipes up to and including 168,3 mm outside diameter.

5.2.9 Where socket welded fittings are employed, the diametrical clearance between the outside diameter of the pipe and the base of the fitting is not to exceed 0,8 mm, and a gap of approximately 1,5 mm is to be provided between the end of the pipe and the internal step at the bottom of the socket.

5.2.10 For welding of carbon, carbon/manganese and low alloy steels, the preheat to be applied will be dependent on the material grade, thickness and hydrogen grading of the welding consumable in accordance with Table 13.5.2 Welding preheat levels for piping, unless welding procedure testing indicates that a higher level is required.

Table 13.5.2 Welding preheat levels for piping

Material Grade Thickness,t (mm) see Note 4 Minimum preheat temperature (°C) See Note 1
Non-low H2 Low H2 see Note 2
Carbon and carbon/manganese grades: t ≤ 15 50 10
320 and 360 t ≥ 15 100 50
Carbon and carbon/manganese grades: t ≤ 15 75 20
410, 460 and 490 t ≥ 15 150 100
1Cr ½Mo t < 13   100
t ≥ 13 See Note 3 150
2¼Cr 1Mo t < 13 See Note 3 150
t ≥ 13 200
½Cr ½Mo ¼V t < 13 See Note 3 150
t ≥ 13 200

Note 1. Where the ambient temperature is 0°C or below, pre-warming of the weld joint is required in all cases.

Note 2. Low hydrogen process or consumables are those that have been tested and have achieved a grading of H15 or better (see Ch 11 Approval of Welding Consumables).

Note 3. Low hydrogen welding process is required for these materials.

Note 4. t = the thickness of the thinner member for butt welds, and the thicker member for fillet and branch welds.

5.2.11 Welding without filler metal is generally not permitted for welding of duplex stainless steel materials.

5.2.12 All welds in high pressure, high temperature pipelines are to have a smooth surface finish and even contour; and where necessary, made smooth by grinding.

5.2.13 Check tests of the quality of the welding are to be carried out periodically.

5.3 Heat treatment after bending of pipes

5.3.1 After forming or bending of pipes, the heat treatments specified in this Section are to be applied unless the pipe material manufacturer specifies or recommends other requirements.

5.3.2 Generally, hot forming is to be carried out within the normalising temperature range. When carried out within this temperature range, no subsequent heat treatment is required for carbon and carbon/manganese steels. For alloy steels, 1Cr ½Mo, 2¼Cr 1Mo and ½Cr ½Mo ¼V, a subsequent stress relieving heat treatment in accordance with Ch 13, 1.16 Post-weld heat treatment at the temperatures and times specified in Table 13.5.4 Post-weld heat treatment requirements for piping is required, irrespective of material thickness.

Table 13.5.3 Heat treatment after bending of pipes

Type of steel Heat treatment required
Carbon and carbon/manganese:
Grades 320, 360, 410, 460 and 490
Normalise at 880 to 940°C
1Cr ½Mo Normalise at 900 to 940°C, followed by tempering at 640 to 720°C
2¼Cr 1Mo Normalise at 900 to 960°C, followed by tempering at 650 to 780°C
½Cr ½Mo ¼V Normalise at 930 to 980°C, followed by tempering at 670 to 720°C
Other alloy steels Subject to special consideration

5.3.3 When hot forming is performed outside the normalising temperature range, a subsequent heat treatment in accordance with Table 13.5.3 Heat treatment after bending of pipes is required.

5.3.4 After cold forming to a radius (measured at the centreline of the pipe) of less than four times the outside diameter, heat treatment in accordance with Table 13.5.3 Heat treatment after bending of pipes is required.

5.3.5 Bending procedures and subsequent heat treatment for other alloy steels will be subject to special consideration.

5.4 Post-weld heat treatment

5.4.1 Post-weld heat treatment is to be carried out in accordance with the general requirements specified in Ch 13, 1.16 Post-weld heat treatment and Ch 13, 4.10 Post-weld heat treatment.

5.4.2 The thickness limits, the recommended soaking temperatures and periods, for application of post-weld heat treatment are given in Table 13.5.4 Post-weld heat treatment requirements for piping.

Table 13.5.4 Post-weld heat treatment requirements for piping

Material Grade Thickness for which post-weld heat treatment is required Soak temperature (°C) see Note 2 Soak period
Carbon and carbon/manganese grades: 320, 360, 410, 460, 490 Over 30 mm 580–620°C 1 hour per 25 mm of thickness, 320, 360, 410, 460, 490 minimum of 1 hour
1Cr ½Mo Over 8 mm 620–660°C 1 hour per 25 mm of thickness, minimum of 1 hour
2¼Cr 1Mo All 650–690°C 1 hour per 25 mm of thickness, minimum of 1 hour
½Cr ½Mo ¼V All, see Note 1 670–720°C 1 hour per 25 mm of thickness, minimum of 1 hour

Note 1. Heat treatment may be omitted for thicknesses up to 8 mm and diameters not exceeding 100mm and minimum service temperature 450°C provided that welding procedure tests have demonstrated acceptable properties in the as welded condition.

Note 2. For materials supplied in the tempered condition, the post weld heat treatment temperature is to be at least 20°C less than the material tempering temperature.

5.4.3 Where the use of oxy-acetylene welding is proposed, due consideration is to be given to the need for normalising and tempering after such welding.

5.5 Non-destructive examination

5.5.1 Non-destructive examination of pipe welds is to be carried out in accordance with the general requirements of Ch 13, 1.11 Non-destructive examination of welds and the following.

5.5.2 Butt welds in Class 1 pipes with an outside diameter greater or equal to 75 mm are to be subject to 100 per cent volumetric and visual inspections. Consideration is to be given to the extent and method of testing applied to butt welds in Class 1 pipes with an outside diameter less than 75 mm.

5.5.3 Butt welds in Class II pipes are to be subjected to at least 10 per cent random volumetric inspections when the outside diameter is 100 mm and greater.

5.5.4 NDE for Class II pipes with a diameter less than 100 mm is to be at the discretion of the Surveyor.

5.5.5 Non-destructive examination procedures, methods and the evaluation of reports are to be in accordance with Ch 13, 4.15 NDE Method and Ch 13, 4.16 Evaluation and reports.

5.5.6 Fillet welds on flange pipe connections of Class I pipes are to be examined by surface crack detection methods.

5.5.7 Weld acceptance criteria shall be in accordance with Ch 13, 4.13 Extent of NDE for Class 1 pressure vessels.

5.6 Repairs to pipe welds

5.6.1 Where non-destructive examinations reveal unacceptable defects in a weld, the defects are to be removed and repaired in accordance with Ch 13, 1.15 Rectification of welds defects. Completed repairs are to be shown by further non-destructive examination to have eliminated the defects.

5.6.2 For pipes with diameter less than 88 mm and where unacceptable defects have been found during nondestructive examination, consideration is to be given to cutting the weld out completely, re-making the weld preparation and re-welding as a new joint (because of the difficulty of making small repairs).

5.6.3 Where repeated weld repairs have to be made to a weld, only two such attempts are to be permitted, thereafter the weld is to be cut apart and removed, and re-welded as a new joint.

5.6.4 Where piping requires post-weld heat treatment weld, repairs to the pressure retaining parts are to be subjected to a subsequent heat treatment. Similarly, where welding is conducted after pressure testing, a further pressure test is to be required unless specific exemption has been agreed.


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.