Section
5 Verification
5.1 General
5.1.1 Independent verification provides the Owner of an asset with assurance on lifecycle
hazard management, safeguarding personnel on an installation and the associated
environment. Verification confirms the suitability of the components/system in
accordance with the requirements defined by the Owner. It involves agreement between
the verifier and the Owner throughout the entire process, typically in a
goal-setting form.
5.1.2 Depending on the country and state where an asset is located, verification can be
regulated or not driven by legislation. In legislative frameworks where verification
is regulated, the intent and scope of verification is driven by the underlying
legislation. An example of such legislative framework is Directive 2013/30/EU on the
Safety of Offshore Oil and Gas Operations, where, through the verification process,
Safety and Environmental Critical Elements (SECE) are established and each examined
for suitability for the intended purpose.
5.1.3 Where a flexible pipe system is identified as a SECE or is otherwise identified as
requiring verification, the associated ancillary equipment should be screened. The
ancillary equipment which provides a role in maintaining the integrity of the
flexible pipe system, from just after installation up to decommissioning, is a SECE
and should be included in the scope of verification.
5.1.4 Under the European Safety Directive, a verification scheme requires
formation of performance criteria for each SECE, known as performance standards.
Performance standards define essential requirements that flexible pipe system must
meet. These performance requirements can include functionality, availability,
reliably, survivability, integration, interactions and dependencies requirements.
With regards to the two latter performance requirements, i.e. interactions and
dependencies, the performance of a flexible pipe system should be assessed in
relation to interfaces stated in Ch 1, 2.2 Definitions 2.2.6.
5.1.5 In the verification scheme, verification tasks should be defined by the Owner and LR
based on the legislation, specifying the nature and frequency of examinations, i.e.
an instruction to the verifier, known as Verification Work Instruction (VWI), on how
to verify the suitability of the SECE.
5.2 Scope
5.2.1 The scope for verification for a flexible pipe system is to confirm the
suitability in accordance with defined performance criteria, not necessarily limited
to recognised Codes or standards, e.g. those stated in Ch 1, 4.2 Scope 4.2.2.
5.2.2 Verification covers design and manufacture, and can be extended to cover
installation, commissioning and continued suitability, i.e. fitness for service and
life extension.
5.3 Overview
5.3.1 Verification assessment, depending on the requirements of the performance standards,
is achieved through a combination of desktop review and physical surveillance
activities.
5.3.2 For new construction, verification is performed through desktop review of design and
installation, and physical surveillance of manufacture of pipe body, manufacture and
assembly of end fittings, manufacture of ancillary equipment, installation and
commissioning including field hydrostatic pressure test, and for unbonded flexible
pipes, annulus vacuum test and whether annulus monitoring is available and
operational.
5.3.3 For continued suitability of aged components/system, verification is performed
through desktop review of fitness for service assessment or life extension analysis,
and physical surveillance of pipe body, end fittings and ancillary equipment.
5.3.4 A sampling approach is permitted for both desktop review and physical
surveillance activities, in accordance with Ch 1, 4.3 Overview 4.3.3.
5.4 Design assessment
5.5 Manufacture assessment
5.6 Installation and as-built assessment
5.6.1 Assessments of installation and as-built are performed through a combination of
desktop review and physical surveillance activities.
5.6.2 Desktop review is performed through the following activities:
- Review of installation analysis;
- Review of installation procedure(s) to confirm that the Owner’s
assurance process ensures that they contain sufficient test parameters,
instructions, procedures, etc. to allow the components to be installed and
tested in accordance with the SECE performance criteria;
- Review of field leak test;
- Confirm by review that the as-built configuration reflects the as-designed
configuration;
- Confirm by review of the master punch list, and/or sample review of the
system’s commissioning records, that all major punch list items or those
that affect performance standard compliance have been closed out;
- For unbonded flexible pipes, confirm by review of annulus vacuum test after
installation that the outer sheath layer is intact and the annulus is at dry
condition.
5.6.3 Physical surveillance should be performed to ensure that the installation activities
are in accordance with manufacturer and Owner installation recommendations and the
accepted specifications and procedures. General visual examination should be
performed to confirm that gas venting system is operational and satisfactory (i.e.
that vent paths are clear). For unbonded flexible pipe, this includes examination of
annulus monitoring system.
5.7 Fitness for service/Life extension assessment
5.7.1 Assessment of fitness for service/ life extension is performed through a combination
of desktop review and physical surveillance activities.
5.7.2 For fitness for service of a flexible pipe system prior to expiry of design life,
desktop review is performed through review of the following aspects:
- Operational procedures;
- Operational history, e.g. flexible pipe bore and annulus history
data (if unbonded), shutdown/startup cycles, depressurisation periods and
any instances of exceedance of environmental design conditions;
- History of modifications, damage, integrity assessment and
repairs/replacements;
- Condition assessment; and
- Integrity assessment and adequacy of proposed repairs/replacements.
5.7.3 For life extension, desktop review is performed through review of the following
aspects:
- Risk assessment by FMECA;
- Operational procedures;
- Operational history, e.g. flexible pipe bore and annulus
history data (if unbonded), shutdown/startup cycles, depressurisation
periods, and environmental loads including any instances of exceedance of
environmental design conditions;
- History of inspection, maintenance and in-place testing, e.g. general visual
inspection, NDE, detailed visual inspection, corrosion reports, cathodic
protection surveys, anomaly reports and gas venting testing;
- History of modifications, damage, integrity assessment and
repairs/replacements;
- Condition assessment;
- Integrity assessment and adequacy of proposed repairs/replacements;
- Re-visit relevant aspects of design described in Ch 1, 4.4 Design assessment for the extended life;
and
- Inspection and maintenance plan.
5.7.4 Physical examination is performed through surveillance of pipe body, end fittings and
ancillary equipment for defects, damage and tests including post-repair tests.
5.7.5 As stress analysis methodology, fatigue SN curves and polymer ageing data are
typically proprietary information, stress, fatigue and ageing evaluation
reassessment are recommended to be performed by the original manufacturer.
5.7.6 Due to immaturity of NDE techniques and failure mechanisms for flexible pipe
products, condition and integrity of layers and components cannot be reliably
measured and verified. At the time of publication of these Guidance Notes, life
extension of static or dynamic flexible riser systems is currently not
recommended.
5.7.7 If recognised Codes or standards are used for life extension, it is a
good engineering practise to use the most up-to-date revision of these even if the
original design of the system had been to an older revision.
5.8 Deliverables
5.8.1 Deliverables should reflect the activities performed by the verifier based on the
scope specified by asset Owner.
5.8.2 The deliverables would be as follows:
- CRS or Owner's preferred comment response system;
- Signed-off VWI;
- Visit report; and
- Verification statement.
Other forms of deliverables may be agreed and delivered based on client's
requirements.
|