Section 3 Stage 02: Technology validation
Clasification Society 2024 - Version 9.40
Clasifications Register Guidance Information - Guidance Notes for Certification through Technology Qualification, January 2022 - Chapter 3 Certification through Technology Qualification process - Section 3 Stage 02: Technology validation

Section 3 Stage 02: Technology validation

3.1 Introduction

3.1.1 Following the verification of the technology through a technology appraisal activity, this stage comprises a series of objective tests that must be completed to confirm that the technology is capable of meeting technical requirements, as identified in the definition of the technology. Equally, the findings highlighted in the technology appraisal report must also be considered during the various qualification activities associated with this stage of the certification process.

3.1.2 The sequence of activities related to validation is illustrated in Figure 3.3.1 Technology validation activities.

Figure 3.3.1 Technology validation activities

3.2 Preparation of a Technology Qualification Plan

3.2.1 This document forms the basis for all activities undertaken during the Validation stage. The inputs to the document are the definition of the technology (see Ch 3, 2.4 Definition of the technology) and the technology appraisal report (see Ch 3, 2.14 Technology Appraisal Report).

3.2.2 The Technology Qualification Plan (TQP) should list all qualification activities that are required in order to provide evidence that the technology has met or exceeded the acceptance criteria for each defined specification as established in the definition of the technology (see Ch 3, 2.4 Definition of the technology). In particular, it should address novel aspects that pose uncertainties and any critical failure mode or other risks identified during the risk assessment (see Ch 3, 2.12 Risk assessment).

3.2.3 Each component identified as a red, amber or yellow must be included in the document indicating how the respective issues of concern can be addressed. Additionally, if components identified as green are considered critical, these should also be addressed in the TQP.

3.2.4 As an independent assessor and in keeping with conflict-of-interest issues, LR (or other external discipline specialists) assessing the technology shall not be involved in the preparation of the TQP. However, the technology developer is free to engage any third-party entity in support of its development to provide expertise concerning intended qualification activities.

3.2.5 As a minimum, a TQP shall consist of two parts, covering the following:

Part A: General
  • Title of the technology seeking certification;
  • Name and contact details of technology developer (as on the application form);
  • Project reference number, as stated on the Technology Appraisal Report;
  • Referenced technology appraisal report number, including version;
  • Scope of the certification;
  • List of referenced documents previously submitted for design review (e.g. basis of design, previous test reports, etc.);
  • Definition of the technology;
  • Summary of technology assessment;
  • Summary of risk assessment;
  • Summary of system readiness assessment;
  • List of external consultants, etc. involved with the development of the TQP (to ensure there is no conflict of interest);
  • Risks (technical & non-technical) to implementation of the TQP;
  • Schedule and sequence of tests; and
  • Management of change process.
Part B: For each identified qualification activity, the following details are required:
  • Brief description of the qualification activity;
  • Impacted components/subsystems, with reference to their unique identifier;
  • What specific aspects of the definition of the technology does the qualification activity target/address;
  • Details of the qualification activity procedure;
  • Details of acceptance criteria;
  • Documents to be submitted prior to testing (e.g. test procedures for approval);
  • Personnel involved with each qualification activity (e.g. responsible, accountable, consulted, informed);
  • Witness points, where LR as an independent assessor is required to be represented;
  • Proposed venues for test (e.g. details of accredited test laboratories); and
  • Documentation that will be produced following testing (e.g. test reports, graphs, etc.).

3.3 Review of technology qualification plan

3.3.1 Following the completion of the TQP, the technology developer is to submit it for approval. The approval process will consider clear links between the definition of the technology (see Ch 3, 2.4 Definition of the technology), the technology and risk assessments highlighted in the technology appraisal report, and the acceptance criteria established at the commencement of the technology verification stage. If any of these are unclear or ambiguous, the technology developer will be notified and requested to update the TQP to demonstrate the above.

3.3.2 Approval for a TQP is granted in the form a document referred to as a ‘Statement of Feasibility’. Upon issuing this document, the technology developer shall not modify the TQP without written consent from LR. This is to ensure that further R&D work conducted by technology developers (or their consultants) does not influence the design under assessment.

3.4 Execution of technology qualification activities

3.4.1 The execution of the qualification activities should strictly follow the schedule and sequence stated in the approved TQP. If there is a deviation, LR should be informed along with the reasons for doing so.

3.4.2 In order to ensure traceability, each test should be linked to a specific subsystem/component using the unique identifier assigned during the technology decomposition activity (see Ch 3, 2.7 Technology decomposition 2.7.6). Additionally, test reports should also link to specific details of the definition of the technology (see Ch 3, 2.4 Definition of the technology) that were addressed.

3.4.3 If, during the execution of various qualification activities it is identified that results from a specific test do not conform to the agreed acceptance criteria, these should be recorded along with the cause and potential reason for noncompliance. These details may assist in further investigation, including the possibility of substituting a qualification activity to understand whether the results received are the same.

3.4.4 A qualification activity can be repeated as often as needed to ensure the results meet or exceed the acceptance criteria as stated in the approved TQP. However, no modification to any approved qualification activity shall be made without approval from LR. Equally, the approved TQP shall not be revised to reflect any modified test procedure or acceptance criteria without the consent of LR.

3.4.5 Any deviation from the approved TQP should follow a documented management of change process, including the possibility for updating the TQP and the definition of the technology appropriately.

3.5 Witnessing of tests

3.5.1 During the development of the TQP, the technology developer should engage with LR to agree which specific qualification activities require independent witnessing. These should be introduced into the test-schedule accordingly.

3.5.2 If LR is required to witness any test, arrangements for visits to a test-site should be planned well ahead of the test date, including the availability of approved test procedures and any relevant background information. LR accepts tests reports from accredited test facilities (i.e. test laboratories that have an ISO 17025 accreditation with a scope for the test being conducted) and hence does not need to witness tests conducted at these sites.

3.6 Submission of test results

3.6.1 The results from each qualification activity should be reported in accordance with their respective details as stated in the TQP. It is important that the outcome of each activity is reported fully and accurately soon after its completion. This supports project progress and provides an up to date understanding of the technology’s status.

3.6.2 If anomalies of any description are discovered during testing, these should be discussed with LR so appropriate decisions can be made concerning further qualification activities.

3.6.3 Copies of all test results should be introduced into a dossier of evidence to support the performance review during the final stage of the certification process.

3.7 Review of test results against acceptance criteria

3.7.1 This activity involves the review of each test result against the associated acceptance criteria to determine if they have been met or exceeded.

3.7.2 As part of this review, the approved test procedure will be referenced to determine if it was followed accurately to obtain the submitted results.

3.8 Final review of submitted test results

3.8.1 Upon satisfactory completion of all qualification activities stated in the TQP, LR will perform a final review of the outcomes from the various qualification activities. While test results would have been reviewed progressively soon after tests (see Ch 3, 3.6 Submission of test results), the purpose of this stage is to confirm the following:
  • The TQP has been fully implemented;
  • All qualification activities have been completed in accordance with the approved TQP;
  • The results from each activity have met the acceptance criteria as stated in the definition of the technology;
  • Any deviation has been suitably reported and an approved management of change process implemented;
  • Any recommendation arising has been suitably addressed; and
  • All uncertainties identified during the technology verification stage have been fully addressed, such that confidence in the CTEs have increased to a level commensurate with equivalent mature technologies.
3.8.2 As part of this review the following activities will be undertaken:
  • A detailed design review of specific subsystems demonstrated during testing; and
  • A critical design review of the entire system/technology against the definition of the technology.

3.9 Issuance of a technology validation report

3.9.1 This is a deliverable from LR which follows the conclusion of the technology validation stage and forms the basis of the next stage of the certification process. It also serves as evidence required by the technology developer confirming that the technology has completed an independent assessment process.

3.9.2 The purpose for the technology validation report is the following:
  • To confirm that the qualification activities have been carried out in accordance with the definition of the technology and approved TQP;
  • To confirm whether the tests results have met or exceeded their respective acceptance criteria;
  • To confirm whether further analysis or testing may be appropriate for certain unresolved uncertainties; and
  • To confirm any limitations, conditions, or recommendations beyond the scope of the assessment.

Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.