| Clasification Society Rulefinder 2016 - Version 9.25
Clasification Society Rules and Regulations - Rules and Regulations for the Classification of Offshore Units, January 2016 - Part 11 PRODUCTION, STORAGE AND OFFLOADING OF LIQUEFIED GASES IN BULK - Chapter 20 Barges and Offshore Units Equipped with Regasification - Section 2 Submission of plans and documentation |
||
Section 2 Submission of plans and documentation2.1 General2.1.1 Documentation, together with the relevant information as detailed in this Section, shall be submitted for consideration. 2.1.2 Any alterations to basic design, construction, materials, manufacturing procedure, equipment, fittings or arrangements of the process shall be re-submitted for approval before the regasification plant is put into operation. 2.2 Systems and arrangements2.2.1 The plans and information required by relevant Sections of these Rules are to be submitted for appraisal. 2.2.2 System description document: a description of the arrangements and the intended
operating philosophy, design criteria and functionality of the regasification system.
It shall include the following information:
2.2.3 Risk based analysis undertaken to a recognised Standard in accordance with LR’s ShipRight procedure ‘Assessment of Risk Based Designs’ and the associated Annex on LNG. The analysis shall be documented so that the risks and how they are eliminated or mitigated are clearly identified, and an appropriate level of safety, dependability and hazardous area classification is demonstrated. 2.2.4 Regasification barge or offshore unit general arrangement. Plans showing the arrangement of all areas where equipment, components and piping systems are located. 2.2.5 Plans for vaporisers, heat exchangers (shell/tube, printed circuit and plate type), LNG drum, liquid receivers and other pressure vessels (see also Pt 5, Ch 11 Other Pressure Vessels). 2.2.6 Plans and documents as required by Pt 6, Ch 1 Control Engineering Systems, showing the automatic controls, alarms and safety systems associated with the regasification system. 2.2.7 The thermodynamic calculations confirming the design send-out rates for the vaporisers. 2.2.8 Capacity calculations for pressure relief valves and discharge pipe vent stack pressure drop calculations. 2.2.9 Piping information is to include:
2.2.10 Hazardous Area Plan for regasification equipment and send-out system. 2.2.11 Interfaces: plans and documents detailing the barge or offshore unit to regasification system interfaces. 2.2.12 Safety system plans: fire-fighting details, gas detection details, fire and general alarm details, all related to the regasification system and to the send-out arrangements. They shall be included in the main safety system plans of the vessel for approval in accordance with these Rules. 2.2.13 Escape plan: details of the arrangements for protection and safe escape in relation to the regasification system and send-out arrangements. 2.2.14 An emergency shutdown (ESD) system cause and effect matrix that shall cover the additional operational scenarios of regasification and barge or offshore unit LNG transfer. This shall be integrated with the ESD main system matrix of the vessel. Where an ESD initiation results in multiple actions, the matrix shall indicate these in the order in which they will be performed. 2.2.15 A functional flow chart of the ESD system and connected systems shall be provided which aligns with the cause and effect matrix and details the functions provided by ESD System. A copy shall be maintained at the regasification control station and on the central control room. 2.2.16 A process shutdown (PSD), cause/effect matrix and design philosophy. 2.2.17 Details of depressurisation and high pressure blowdown philosophy and arrangements. 2.2.18 Ancillary systems or additional equipment such as blending facilities, odorizers, dew point correction/ dehumidification, control and monitoring facilities where these are to be considered as part of the classed equipment. 2.2.19 Operating manuals shall be submitted. The content of the manuals shall include but
not be limited to:
|
||
|
|
||
|