| 
                  
                  
                    
                     Section 
                     6 Procedures for testing tanks and tight boundaries
                  
                     
                        
                          6.1 General
                        
                           
                           
                              
                              
                              6.1.1 The test procedures detailed in this Section are to be used to confirm
                                 the watertightness of tanks and watertight boundaries, the structural adequacy of
                                 tanks and weathertightness of structures.
                               
                     
                        
                          6.2 Application
                        
                           
                           
                              
                              
                              6.2.1 The testing requirements for gravity tanks, defined as tanks subject to a
                                 vapour pressure not greater than 70 kN/m2, and other boundaries required
                                 to be watertight or weathertight, are to be tested in accordance with this Section.
                                 Tests are to be carried out in the presence of a Surveyor at a stage sufficiently
                                 close to completion such that the strength and tightness are not subsequently
                                 impaired and prior to any ceiling and cement work being applied over joints. 
                               
                              
                              
                              6.2.2 The testing of structures not listed in this Section are to be specially
                                 considered.
                               
                     
                        
                          6.3 Test types
                        
                           
                           
                              
                              
                              6.3.1 The types of test specified in this Section are:
                                  
                                    
                                       Structural test: which is to be conducted to verify the tightness and
                                       structural adequacy of the construction of tanks. This may be a hydrostatic
                                       test or, where the situation warrants, a hydropneumatic test. 
                                    
                                        Leak test:  which is to be used to verify the tightness of a
                                       boundary. Unless a specific test is indicated, this may be a hydrostatic,
                                       hydropneumatic test, air or other medium test. 
                                     
                     
                        
                          6.4 Structural test procedures
                        
                           
                           
                           
                           
                           
                              
                              
                              6.4.2 A hydrostatic test or hydropneumatic test may be carried out afloat to
                                 confirm the structural adequacy of tanks, provided that a leak test is carried out
                                 and the results are confirmed as satisfactory . Where possible, the leak test is to
                                 be carried out before the unit is afloat.
                               
                              
                              
                              6.4.3 For tanks of the same structural design, configuration and the same
                                 general workmanship, as determined by the attending Surveyor, a structural test may
                                 be carried out on only one tank, provided all subsequent tanks are tested for leaks
                                 by an air test.
                               
                              
                              
                              6.4.4 Where the structural adequacy of a tank has been verified by structural
                                 testing on a previous vessel in a series, tanks of structural similarity on
                                 subsequent vessels within that series (which are built at the same shipyard
                                 following the same construction, welding and quality procedure) may be exempt from
                                 such testing, provided that the watertightness of all exempt tanks is verified by
                                 leak tests and thorough inspection. However, structural testing is to be carried out
                                 for at least one tank of each type of tank on  every vessel in the series. The
                                 relaxation to accept leak testing and thorough inspections instead of a structural
                                 test on subsequent vessels in a series does not apply to cargo space boundaries
                                 adjacent to other compartments or to the boundaries of tanks for segregated cargoes
                                 or pollutants.
                               
                              
                              
                              6.4.6 For watertight boundaries of spaces other than tanks, excluding chain
                                 lockers, structural testing may be exempted, provided that the watertightness in all
                                 boundaries of exempted spaces are verified by leak tests and thorough
                                 inspection.
                               
                              
                              
                              6.4.7 Consideration is to be given to the selection of tanks to be structurally
                                 tested. Selected tanks are to be chosen so that all representative structural
                                 members are tested for the expected tension and compression.
                               
                     
                        
                          6.5 Leak test procedures
                        
                           
                           
                              
                              
                              6.5.1 Where a leak test is specified in Table 3.6.1 Testing
                                    requirements, unless
                                 specified otherwise, a tank air test, compressed air fillet weld test, or vacuum box
                                 test is to be carried out in accordance with the applicable requirements of Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.4 to Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.6. A hydrostatic or hydropneumatic
                                 test conducted in accordance with the applicable requirements of Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.1 and Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.2 will be accepted as a leak test on the condition that safe
                                 access to all joints being examined is provided. Where a hydrostatic or
                                 hydropneumatic test is applied as a leak test, the external boundaries are to be
                                 free of any liquid residue prior to the commencement of the test. 
                               
                              
                              
                              6.5.3 Air tests of joints may be conducted at any stage during construction
                                 provided that all work that might affect the tightness of the joint is completed
                                 before the test is carried out.
                               
                              
                              
                              6.5.4 Where acceptable to the attending Surveyor, provided that careful visual inspections
                                 show a continuous uniform weld profile shape, free from repairs, and the results of
                                 selected NDE testing show no significant defects, the leak testing of automatic butt
                                 welds and semi-automatic (flux core arc welding) butt welds may be omitted.
                               
                     
                        
                          6.6 Definitions and details of tests
                        
                           
                           
                              
                              
                              6.6.1 
                                 Hydrostatic test is a test conducted by filling a space with a liquid to a
                                 specified head. Unless another liquid is approved, the hydrostatic test is to
                                 consist of filling a space with either fresh or sea-water, whichever is appropriate
                                 for the space being tested, to the level specified in Table 3.6.1 Testing
                                    requirements. For tanks intended to carry cargoes of a higher
                                 density than the test liquid, the head of the liquid is to be specially considered. 
                               
                              
                              
                              6.6.2 
                                 Hydropneumatic test is a combination of a hydrostatic test and a tank air
                                 test, consisting of partially filling a tank with water and conducting a tank air
                                 test on the unfilled portion of the tank. A hydropneumatic test, where approved, is
                                 to be such that the test condition in conjunction with the approved liquid level and
                                 air pressure will simulate the actual loading as far as practicable. The
                                 requirements for tank air testing shown in Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.4 are to be adhered to. 
                               
                              
                              
                              6.6.3 
                                 Hose test is a test used to verify the tightness of joints with a jet of
                                 water. The jet of water is to be directed perpendicular to the joint. It is to be
                                 carried out with the pressure in the hose nozzle maintained at not less than 2,0 bar
                                 during the test. The hose nozzle is to have a minimum inside diameter of 12 mm and
                                 is to be situated no further than 1,5 m from the joint. Where a hose test is not
                                 practical because of possible damage to machinery, electrical equipment insulation
                                 or outfitting items, it may be replaced by a careful visual examination of welded
                                 connections, supported by an ultrasonic or penetration leak test, or an equivalent,
                                 see SOLAS Reg. II-1/Regulation 11 - Initial testing of watertight bulkheads, etc. 
                              
                              
                              6.6.4 
                                 Tank air test is to be used to verify the tightness of a compartment by means
                                 of an air pressure differential and leak indicator solution. An efficient indicating
                                 solution (e.g. soapy water) is to be applied to the weld or penetration being tested
                                 and is to be examined whilst an air pressure differential of not less than 0,15 bar
                                 is applied by pumping air into the compartment. Arrangements are to be made to
                                 ensure that any increase in air pressure does not exceed 0,30 bar. A U-tube with a
                                 height sufficient to hold a head of water corresponding to the required test
                                 pressure is to be used for verification and to avoid overpressure. The
                                 cross-sectional area of the U-tube is not to be less than that of the pipe supplying
                                 air to the tank. Alternatively two calibrated pressure gauges may be considered
                                 acceptable. All boundary welds including pipe connections in the compartment are to
                                 be examined twice. The first is to be examined immediately upon applying the leak
                                 indication solution; the second approximately five minutes afterwards. 
                               
                              
                              
                              6.6.5 
                                 Compressed air fillet weld test. This test consists of compressed air being
                                 injected into one end of a fillet welded joint and the pressure verified at the
                                 other end of the joint by a pressure gauge on the opposite side. Pressure gauges are
                                 to be arranged so that an air pressure of at least 0,15 bar above atmospheric
                                 pressure can be verified at each end of all passages within the portion being
                                 tested. A leak indicator solution is to be applied and the weld line examined for
                                 leaks. A compressed air test may be carried out for partial penetration welds where
                                 the root face is greater than 6 mm. 
                               
                              
                              
                              6.6.6 
                                 Vacuum box test  is a test used to verify the tightness of joints by means of
                                 a localised air pressure differential and indicator solution. The test is to be
                                 conducted with the use of a box with air connections, gauges and an inspection
                                 window that is to be placed over the joint being tested with a leak indicator
                                 solution applied. Air within the box is to be removed by an ejector to create a
                                 reduction in pressure. The pressure inside the box during the test is to be
                                 maintained between 0,20 to 0,26 bar. 
                               
                              
                              
                              6.6.7 
                                 Ultrasonic test may be used where a hose test is not practical to verify the
                                 tightness of a boundary, see
                                 Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.3. An arrangement of ultrasonic echo
                                 transmitters is to be placed inside a compartment and a receiver outside. The
                                 receiver is to be used to detect any leaks in the compartment. 
                               
                              
                              
                              6.6.8 
                                 Penetration test may be used where a hose test is not practical to assess
                                 butt welds, see
                                 Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.3, by applying a low surface
                                 tension liquid to one side of a compartment boundary. When no liquid is detected on
                                 the opposite side of the boundary after expiration of a defined period of time, the
                                 verification of tightness of the compartment’s boundary may be assumed. A developer
                                 solution may be applied on the other side of the weld to aid leak detection.
                               
                              
                              
                              6.6.9 Other methods of testing may be considered and are to be agreed by LR
                                 prior to commencement of testing.
                               
                     
                        
                          6.7 Application of coating
                        
                           
                           
                              
                              
                              6.7.1  A final coating may be applied over automatic butt welds before the completion of a
                                 leak test, provided that careful visual inspections show continuous uniform weld
                                 profile shape, free from repairs, and the results of selected NDE testing show no
                                 significant defects. For all other joints, the final coating is to be applied after
                                 the completion of a leak test. The Surveyor reserves the right to require a leak
                                 test prior to the application of the final coating over automatic erection butt
                                 welds.
                               
                              
                              
                              6.7.2 Any temporary coating which may conceal defects or leaks is to be applied
                                 at a time as specified for the final coating, see
                                 Pt  4, Ch  3,  6.7 Application of coating 6.7.1. This requirement does not apply to shop primer. 
                               
                     
                        
                          6.8 Safe access to joints
                        
                           
                           
                              
                              
                              6.8.1 For leak tests, safe access to all joints under examination is to be
                                 provided.
                                 
                                  
                                    Table 3.6.1 Testing
                                          requirements
                                       
                                          
                                             | Item to be tested | Testing procedure | Test requirement |  
                                             | Double bottom tanks,
                                                see Note 1 | Leak &
                                                structural | The greater of: 
                                                   head of water up to the top of the
                                                      overflow
                                                   head of water 2,4 m above top of tank,
                                                      see Note 2 
                                                   head of water up to bulkhead deck  |  
                                             | Combined double bottom and
                                                hopper side tanks | Leak &
                                                structural | The greater of: 
                                                   head of water up to the top of the
                                                      overflow
                                                   head of water representing the maximum
                                                      pressure experienced in service
                                                    |  
                                             | Double bottom voids,
                                                see Note 3 | Leak |  |  
                                             | Double side tanks | Leak &
                                                structural | The greater of: |  
                                             | Combined double bottom,
                                                lower hopper and topside tanks | Leak &
                                                structural | 
                                                   see Note 2 head of water up to the top of the
                                                      overflow
                                                   head of water 2,4 m above top of tank, |  
                                             | Topside tanks | Leak &
                                                structural | 
                                                   head of water up to bulkhead deck |  
                                             | Double side voids | Leak |  |  
                                             | Deep tanks (other than
                                                those listed) | Leak &
                                                structural | The greater of: 
                                                   see Note 2head of water up to the top of the
                                                      overflow
                                                   head of water 2,4 m above top of tank, |  
                                             | Cargo oil tanks, and fuel
                                                oil bunkers | Leak &
                                                structural | The greater of: 
                                                   see Note 2head of water up to the top of the
                                                      overflow
                                                   head of water 2,4 m above top of tank, |  
                                             | Scupper and discharge
                                                pipes in way of tanks | Leak &
                                                structural | 
                                                   head of water up to top of tank, see
                                                      Note 2, plus setting of fitted pressure-relief valve
                                                      
                                                    |  
                                             | Peak tanks, see
                                                Note 4 | Leak &
                                                structural | The greater of:: 
                                                   head of water up to the top of the
                                                      overflow
                                                   head of water 2,4 m above top of tank,
                                                      see Note 2 
                                                    |  
                                             | Fore peak voids | Leak and
                                                structural | Head of water up to the
                                                bulkhead deck, see Note 8 |  
                                             | Aft peak voids, see
                                                Note 4 | Leak |  |  
                                             | Cofferdams | Leak |  |  
                                             | Watertight
                                                bulkheads | Leak | See Note 5 |  
                                             | Superstructure end
                                                bulkhead | Leak |  |  
                                             | Watertight doors below
                                                freeboard or bulkhead deck | Leak | See Notes 6 & 12 |  
                                             | Double plate rudder
                                                blade | Leak |  |  
                                             | Shaft tunnel clear of deep
                                                tanks | Leak | See Note 5 |  
                                             | Shell doors when fitted in
                                                place | Leak | See Notes 5 & 7 |  
                                             | Weathertight doors, hatch
                                                covers and closing appliances | Leak | See Note 5 |  
                                             | Lube oil sump tanks and
                                                other similar tanks/spaces under main engines | Leak | See Note 5 |  
                                             | Steel hatch covers fitted
                                                to the cargo oil tanks and cargo holds of ships used for the
                                                alternate carriage of oil cargo and dry bulk cargo | Leak | See Note |  
                                             | Chain locker | Leak &
                                                structural | Head of water up to top of
                                                chain pipe |  
                                             | Independent tanks, and
                                                edible liquid tanks | Leak &
                                                structural | The greater of: 
                                                   see Note 2 head of water up to the top of the
                                                      overflow
                                                   head of water 0,9 m above top of tank, |  
                                             | Ballast ducts | Leak &
                                                structural | The greater of: 
                                                   ballast pump maximum pressuresetting of pressure-relief valve |  
                                             | Chemical tanks | Leak &
                                                structural | The greater of: 
                                                   head of water 2,4 m above top of tank,
                                                      see Note 2 
                                                   head of water up to top of tank, see
                                                      Note 2, plus setting of fitted pressure-relief valve
                                                      
                                                    |  
                                             | NOTES 
                                                   1. Including tanks arranged in
                                                   accordance with the provisions of SOLAS Reg. II-1/Regulation 9 - Double bottoms in passenger ships and cargo ships other than tankers. 
                                                 
                                                   2. Top of tank is the deck
                                                   forming the top of the tank, excluding any hatchways. In
                                                   holds for liquid cargo or ballast with large hatch openings,
                                                   the top of tank is to be taken to the top of the hatch.
                                                 
                                                   3. Including duct keels and dry
                                                   compartments arranged in accordance with the provisions of
                                                   SOLAS Reg. II-1/Regulation 9 - Double bottoms in passenger ships and cargo ships other than tankers and Reg. II-1/11.2, as
                                                   well as voids used for the protection of fuel oil tanks and
                                                   pump rooms arranged in accordance with the provisions of
                                                   MARPOL Annex I, Reg. 12A and Reg. 22. 
                                                 
                                                   4.  Testing of the aft peak is
                                                   to be carried out after the sterntube has been fitted.
                                                 
                                                   5.  A hose test will be
                                                   considered, see
                                                   Pt  4, Ch  3,  6.5 Leak test procedures 6.5.2 and Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.3. 
                                                 
                                                   6. Watertight doors not
                                                   confirmed watertight by a prototype test are to be subject
                                                   to a hydrostatic test, see SOLAS Reg. II-1/Regulation 16 - Construction and initial tests of watertight closures. 
                                                 
                                                   7. For shell doors providing
                                                   watertight closure, watertightness is to be demonstrated
                                                   through prototype testing before installation. The testing
                                                   procedure is to be agreed with LR prior to testing.
                                                 8. Where demonstrated to be impracticable, the structural
                                                   testing of fore peak void spaces may be exempted subject to
                                                   the agreement of the attending Surveyor.
                                                 9. Where a cargo tank is designed for the carriage of cargoes
                                                   with a specific gravity greater than 1,0, an appropriate
                                                   additional head is to be considered.
                                                 10. Where air vents are fitted below the top of the coaming,
                                                   adequate blanking off of these vents may be required prior
                                                   to the commencement of the test.
                                                 
                                                   11. Other testing methods
                                                   listed in Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.7 and Pt  4, Ch  3,  6.6 Definitions and details of tests 6.6.8 may be
                                                   considered, subject to adequacy of such testing methods
                                                   being verified, see SOLAS Reg. II-1Regulation 11 - Initial testing of watertight bulkheads, etc.
                                                   
                                                 12. All watertight doors are to be hose tested after
                                                   installation. Hose testing is to be carried out from each
                                                   side of a door unless, for a specific application, flooding
                                                   is anticipated from only one side. Where a hose test is not
                                                   practicable because of possible damage to machinery,
                                                   electrical equipment insulation or outfitting items, it may
                                                   be replaced by an ultrasonic leak test or an equivalent
                                                   test.
                                                 |  |