Section
3 Best practice for commissioning testing
3.1 General
3.1.1 The service supplier carrying out the commissioning testing of the BWMS is to be
familiar with the system, in terms of its operation principles and its System Design
Limitations/operational limitations. These will be clearly defined in the IMO Type
Approval Certificate.
3.1.2 It is advisable that the shipowner discusses the System Design
Limitations/operational limitations of the BWMS and intended uptake water with the
service supplier and provides the service supplier with all necessary documentation,
such as copies of Type Approval certificates, the Operation, Maintenance &
Safety Manual, etc. Some systems will have limitations for salinity, temperature, UV
transmissions, etc. of the uptake water, for example.
3.1.3 The shipowner should ensure that the ballast tanks have been cleared of sediment
prior to the commencement of commissioning testing. Sediment is to be disposed of
responsibly and in accordance with local regulations. The ship’s crew are to operate
the BWMS during commissioning testing. It is therefore important the crew are
familiar with and trained in the correct operation of the BWMS before commissioning
testing commences.
3.1.4 Some BWMS, such as UV types, are able to operate in different modes which can alter
the dosing. The shipowner should ensure that during commissioning testing the system
is operated in its IMO Type Approved mode, which may use a lower dose compared to
United States Coastguard (USCG) Type Approved mode.
3.1.5 The safety of persons involved in the commissioning testing is essential, and due
consideration should be given to the BWMS technology used. For example, some BWMS
use active substances which can have harmful effects. Material Data Safety sheets
are to be available and consulted.
3.1.6 Commissioning testing comprises two assessments. In addition to assessing the
biological performance by sampling and analysis of the ballast water, it is required
to assess the system’s self-monitoring parameters for correct operation of BWMS.
Service suppliers are to perform both assessment of the biological sampling and
assessment of self-monitoring parameters and submit findings in the form of a
report. It is therefore important the ship’s crew are familiar with self-monitoring
details and able to assist in providing access to gather the required information to
perform the commissioning testing effectively.
3.2 Sampling and analysis assessment for commissioning testing
3.2.1 The sampling and analysis of the ballast water for commissioning testing is to verify
that the BWMS is installed and functioning correctly. The purpose is not to
revalidate the Type Approval testing.
3.2.2 Sampling
- Sampling should be conducted for compliance with the IMO
International Convention for the Control and Management of Ships'
Ballast Water and Sediments, 2004, regulation D-2. Samples should be
collected to conduct analysis on two of the defined organism size classes,
greater than or equal to 50 µm and greater than or equal to 10 µm–50 µm, in
accordance with IMO BWM.2/Circ.70, rev1.
- A representative sample should be collected, in accordance with
Guidelines for Ballast Water Sampling (G2). The only exception is
during sampling at uptake, where ambient water is collected.
- Discharge sampling is to be conducted in a way that minimises mortality of
organisms, with a sample volume of at least 1 m³. This will result in using
a standard plankton net arrangement, or ISO standard sample collection
devices for ballast water sampling. Time integrated sampling over the whole
discharge operation would be recommended. Smaller sampling volumes may be
acceptable, provided they are validated and accepted by LR. It is advisable
for service suppliers to submit validation reports and get approval in
advance of commissioning testing.
- Typically, indicative analysis equipment requires a small volume of water
for analysis. It should be demonstrated that the concentration of
sub-samples is representative of the sample volume collected. Full
information, including methodology and mixing for sub-samples, should be
provided to LR and the shipowner.
3.2.3 Analysis
- Samples should be analysed using indicative analysis equipment.
Indicative analysis is defined in BWM.2/Circ.42/Rev.1, as may be
amended. This is a minimum requirement as per BWM.2/Circ.70, rev1, as
amended.
- Detailed analysis may be used, in place of indicative analysis, as detailed
analysis provides more accurate results. The detailed analysis methodology
should be suitably validated and approved by LR. Should samples be sent to a
laboratory, for preparation and subsequently to conduct detailed analysis,
then the detailed analysis should be carried out under an approved method(s)
in accordance with ISO/IEC 17025, or equivalent.
- LR requires indicative analysis equipment to be approved for its
intended purpose. It is understood that currently there are few types of
indicative analysis equipment available for the analysis of the greater than
or equal to 50 µm organism size class. As an alternative, a combination of
detailed and indicative analysis may be used.
- Uptake water does not need to meet specified challenge conditions. The
uptake water should be suitable for treatment by the BWMS, i.e. not outside
of its System Design Limitation. Hence, characterising the physical water
condition of uptake water is important.
3.3 Self-monitoring parameters assessment for commissioning testing
3.3.1 The BWMS may have a range of self-monitoring parameters that are fundamental to
monitoring the correct biological performance and system operation, and these are to
be monitored and recorded simultaneously, as part of the commissioning test.
Self-monitoring parameters should be recorded on both the uptake and the discharge
cycles during the commissioning testing. Often, the set points for the
self-monitoring parameters are set during the commissioning of the system and can be
ship-specific. The Operation, Maintenance and Safety Manual, Type Approval
certificate and other documentation from the manufacturer, will provide information
on self-monitoring parameters.
3.3.2 The set points for the self-monitoring parameters should be recorded as
part of the commissioning test. When the system is in operation, comparison against
these set points can be made. The Human Machine Interface (HMI) screen of the BWMS
should provide real-time updates of the parameters. Subsequently, these will be
recorded in the system’s log. Some parameters will be BWMS technology specific,
others generic. Table 1.3.1 Parameter examples gives a
non-exhaustive list of parameters that might be relevant:
Table 1.3.1 Parameter examples
Parameter
|
Unit (s)
|
Applicable system example
|
Flow rate
|
m3/hr
|
Most inline systems
|
Treated volume
|
m3
|
In-tank systems
|
Ultraviolet (UV) dose (UVD)
|
mJ/cm2, J/m2
|
UV systems
|
UV intensity (UVI)
|
mw/cm2, w/m2
|
UV systems
|
UV transmission (UVT)
|
%
|
UV systems
|
Filter inlet pressure
|
Bar, mbar
|
System with filter
|
Filter differential pressure
|
Bar, mbar
|
System with filter
|
Total residual oxidant (TRO)
|
ppm
|
Active substance systems
|
Dissolved ozone
|
ppm
|
Ozone systems
|
Conductivity
|
µs/cm
|
Systems with salinity restriction
|
Salinity
|
PSU
|
Systems with salinity restriction
|
3.3.3 Depending upon the design of the BWMS, it may be necessary for some of these
self-monitoring parameters to be verified by sampling. For example, TRO measurement
can be verified by analysing discharge water with a portable calorimeter. This would
verify that the BWMS discharge does not exceed the Maximum Allowable Discharge
Concentration (MADC) limit, and that it is installed and functioning correctly.
3.3.4 The self-monitoring parameters will be displayed and available in the
BWMS control and monitoring system. Photographic evidence of the BWMS HMI screen
with above parameters and BWMS alarm log should be submitted with the report. These
photos should be taken periodically throughout the commissioning test.
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
 |
|