Section 1 External structure
Clasification Society 2024 - Version 9.40
Clasifications Register Rules and Regulations - Rules and Regulations for the Construction & Classification of Submersibles & Diving Systems, July 2022 - Part 4 Exostructure, Stability and Corrosion Protection - Chapter 1 Exostructure - Section 1 External structure

Section 1 External structure

1.1 General

1.1.1 LR does not lay down any strict environmental or pressure differential loadings in these Rules (except as in Pt 4, Ch 1, 1.1 General 1.1.2 to Pt 4, Ch 1, 1.1 General 1.1.4). The designer is, however, to satisfy LR that the loadings used are satisfactory and the Class will be based in those conditions used.

1.1.2 Tanks forming an integral part of a submersible are generally to be suitable for a hydraulic test pressure of 1,5 times the maximum differential pressure for which they are designed to be used in service.

1.1.3 Hull structure which does not form part of the pressure hull or other pressurized system is to be designed with a load factor of not less than 2 against failure under the worst combination of loading during service operations. Failure, in this context, is assumed if the component has fractured, collapsed or distorted to an extent rendering it, or associated components, inoperable or dangerous to operate in the designed manner.

1.1.4 Where practicable, the outer fairing, other non-pressurized structure or equipment attachment to a submersible, should be designed so that in the event of shock from collision or similar accident, local collapse can occur sufficient to avoid acceleration in excess of 3g for the unit as a whole, without causing the loss of the unit. A clearance of not less than 150 mm between the fairing and critical life-support components should be arranged, where practicable, in the areas most susceptible to damage. Fairing or other protection should be arranged in way of hull penetrations; especially of umbilicals, to minimize damage (e.g. being sheared off).

1.1.5 Diving baskets are to be provided with adequate mechanical protection to protect the divers and to prevent damage to the critical components of the basket during handling operations and other normal or emergency operations. The lower section of the basket is to be provided with a platform enabling the divers to stand safely. Baskets are to be provided with internal handholds to support the divers and gates or chains to prevent the divers from falling out.

1.1.6 For the purpose of the design calculations the un-factored acceleration of the submersible from the point of view of collisions should be generally assumed to be not less than 3g in the horizontal direction. The vertical acceleration, including those during launch and recovery of the unit, should be assumed to be not less than 2g. Generally the sea state for manned submersible handling systems should not exceed Sea State 4. Special consideration will be given to cases where diving operations service in more severe sea state is envisaged for manned diving operations.

1.1.7 The effect of loads due to launching and recovery together with wave impact should also be examined. Particular attention should be paid to the strength of the lifting point attachment to the submersible.

1.1.8 The Builder shall supply material and welding specifications including procedure tests required for the fabrication. Procedure qualification tests are to be carried out using representative materials and thicknesses. These tests are to be witnessed by the LR Surveyor and are to be to the Surveyor’s satisfaction. The Builder shall maintain a complete record of procedure qualification test results.

1.1.9 Calculations used to establish the adequacy of the exostructure should be submitted for approval at an early stage. The calculations should take account of the hydrostatic loads due to submergence together with loads due to manoeuvring and underwater tasks to be undertaken. In addition forces due to collision with underwater obstructions should be taken into account.

1.1.10 The design methods used to establish the adequacy of the exostructure, including buoyancy/ballast tanks, may follow any recognized engineering practice and may be performed using a specialist software program for structural analysis and design. The maximum pressure differential, wave slam and similar loadings are to be adequately catered for.

1.1.11 The Operating Manual is to specify the design loadings used for class approval and the unit is not to be operated in any environment which would produce more severe loadings (Pt 1, Ch 3, 4.4 Plans, documents and calculations 4.4.1 refers).


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.