1.2.1 Before the expiry date of the certificate, the manufacturer may apply to LR for
renewal of the certificate.
1.2.2 A new works inspection will be completed by the LR Surveyor to confirm that the
processes of manufacture, including supervision, quality control and record-keeping,
are of an adequate standard and that storage conditions and facilities were found to
be satisfactory, concerning the wire-gas combinations that are certified.
1.2.3 Certificate renewal is also subject to the certified consumables being
re-tested to the original test programme every three years. These tests along with
annual tests, Ch 3, 1.3 Annual testing of consumables, are to be
witnessed by the LR Surveyor.
1.2.4 Provided the works inspection and all testing are successful, a new certificate is
issued certifying the manufacturing plant for a further three years.
1.2.5 Continued product certification is dependent upon the manufacturing plant
certification remaining valid.
1.2.6 If the manufacturer has no products certified or if all products become overdue this
will void the manufacturing plant certification.