5.1 Three methods of carrying out ballast water
exchange at sea have been identified as acceptable by the Organization.
Each has particular safety aspects associated with it that should
be considered when selecting the method(s) to be used on a particular
ship.
5.2 When identifying the ballast water exchange
method(s) for the first time for a particular ship, an evaluation
should be made which should include:
-
.1 the safety margins for stability and strength
contained in allowable seagoing conditions, as specified in the approved
trim and stability booklet and the loading manual relevant to individual
types of ships. Account should also be taken of the loading conditions
and the envisaged ballast water exchange method or methods to be used;
-
.2 the ballast pumping and piping system taking
account of the number of ballast pumps and their capacities, size
and arrangements of ballast water tanks; and
-
.3 the availability and capacity of tank vents
and overflow arrangements, for the flow through method, the availability
and capacity of tank overflow points, prevention of under and over
pressurization of the ballast tanks.
5.3 Particular account should be taken of the
following:
-
.1 stability which is to be maintained at all
times and not less than those values recommended by the Organization
or required by the Administration;
-
.2 longitudinal stress, and where applicable torsional
stress values, not to exceed permitted values with regard to prevailing
sea conditions;
-
.3 exchange of ballast in tanks where significant
structural loads may be generated by sloshing action in the partially
filled tank to be carried out in favourable sea and swell conditions
such that the risk of structural damage is minimized;
-
.4 wave-induced hull vibrations when carrying
out ballast water exchange;
-
.5 limitations of the available methods of ballast
water exchange in respect of sea and weather conditions;
-
.6 forward and aft draughts and trim, with particular
reference to bridge visibility, slamming, propeller immersion and
minimum forward draft; and
-
.7 additional work loads on the master and crew.
5.4 Having undertaken an evaluation for a particular
ship and the exchange method or methods to be used, the ship should
be provided with procedures, advice and information appropriate to
the exchange method(s) identified and ship type in the Ballast Water
Management Plan. The procedures, advice, and information in the Ballast
Water Management Plan, may include but is not limited to the following:
-
.1 avoidance of over and under-pressurization
of ballast tanks;
-
.2 free surface effects on stability and sloshing
loads in tanks that may be slack at any one time;
-
.3 maintain adequate intact stability in accordance
with an approved trim and stability booklet;
-
.4 permissible seagoing strength limits of shear
forces and bending moments in accordance with an approved loading
manual;
-
.5 torsional forces;
-
.6 forward and aft draughts and trim, with particular
reference to bridge visibility, propeller immersion and minimum forward
draft;
-
.7 wave-induced hull vibrations when performing
ballast water exchange;
-
.8 watertight and weathertight closures (e.g.
manholes) which may have to be opened during ballast exchange must
be re-secured;
-
.9 maximum pumping/flow rates – to ensure
the tank is not subjected to a pressure greater than that for which
it has been designed;
-
.10 internal transfers of ballast;
-
.11 admissible weather conditions;
-
.12 weather routeing in areas seasonably affected
by cyclones, typhoons, hurricanes, or heavy icing conditions;
-
.13 documented records of ballasting and/or de-ballasting
and/or internal transfers of ballast;
-
.14 contingency procedures for situations which
may affect ballast water exchange at sea, including deteriorating
weather conditions, pump failure and loss of power;
-
.15 time to complete the ballast water exchange
for each tank or an appropriate sequence thereof;
-
.16 continual monitoring of the ballast water
operation; monitoring should include pumps, levels in tanks, line
and pump pressures, stability and stresses;
-
.17 a list of circumstances in which ballast water
exchange should not be undertaken. These circumstances may result
from critical situations of an exceptional nature or force majeure due
to stress of weather, known equipment failures or defects, or any
other circumstances in which human life or safety of the ship is threatened;
-
.18 ballast water exchange at sea should be avoided
in freezing weather conditions. However, when it is deemed absolutely
necessary, particular attention should be paid to the hazards associated
with the freezing of overboard discharge arrangements, air pipes,
ballast system valves together with their means of control, and the
build up of ice on deck; and
-
.19 personnel safety, including precautions which
may be required when personnel are required to work on deck at night,
in heavy weather, when ballast water overflows the deck, and in freezing
conditions. These concerns may be related to the risks to the personnel
of falling and injury, due to the slippery wet surface of the deck
plate, when water is overflowing on deck, and to the direct contact
with the ballast water, in terms of occupational health and safety.
5.5 During ballast water exchange sequences there
may be times when, for a transitory period, one or more of the following
criteria cannot be fully met or are found to be difficult to maintain:
-
.1 bridge visibility standards (SOLAS V/22);
-
.2 propeller immersion; and
-
.3 minimum draft forward.
5.6 As the choice of acceptable ballast water
exchange sequences is limited for most ships, it is not always practicable
to dismiss from consideration those sequences where transitory noncompliance
may occur. The practical alternative would be to accept such sequences
provided an appropriate note is placed in the Ballast Water Management
Plan to alert the ship's master. The note would advise the master
of the nature of the transitory non-compliance, that additional planning
may be required and that adequate precautions need to be taken when
using such sequences.
5.7 In planning a ballast water exchange operation
that includes sequences which involve periods when the criteria for
propeller immersion, minimum draft and / or trim and bridge visibility
cannot be met, the Master should assess:
-
.1 the duration(s) and time(s) during the operation
that any of the criteria will not be met;
-
.2 the effect(s) on the navigational and manoeuvring
capabilities of the ship; and
-
.3 the time to complete the operation.
5.8 A decision to proceed with the operation should
only be taken when it is anticipated that:
-
.1 the ship will be in open water;
-
.2 the traffic density will be low;
-
.3 an enhanced navigational watch will be maintained
including if necessary an additional look out forward with adequate
communications with the navigation bridge;
-
.4 the manoeuvrability of the vessel will not
be unduly impaired by the draft and trim and or propeller immersion
during the transitory period; and
-
.5 the general weather and sea state conditions
will be suitable and unlikely to deteriorate.
5.9 On oil tankers, segregated ballast and clean
ballast may be discharged below the water line at sea by pumps if
the ballast water exchange is performed under the provisions of Regulation D-1.1 of the International
Convention for the Control and Management of Ships' Ballast Water
and Sediments, provided that the surface of the ballast water has
been examined either visually or by other means immediately before
the discharge to ensure that no contamination with oil has taken place.