6.1.2 On
completion, tanks and reservoirs for service and storage of system
fluids are to be tested by a head of water equal to the maximum to
which the tanks may be subjected, but not less than 2,5 m above the
crown of the tank.
6.1.3 After
installation on board, piping systems together with associated fittings
that are under internal pressure, are to be subjected to a running
test at the intended maximum working pressure.
6.1.4 Testing
is to cover the following items:
-
Verification
of control, alarm, safety systems.
-
Tests simulating
failure of waste system equipment and pumps to verify correct functioning
of alarms and systems in service.