10.1.1 Welding,
weld procedures, approval of welders and the fabrication of pipelines
to be in accordance with a recognized code, standard tor specification
acceptable to LR. For example, API STD 1104 — Standard
for Welding Pipelines and Related Facilities. Weld procedures
are to be qualified under the survey of LR.
10.1.2 The type
of disposition of connections and sequences of welding are to be planned
so that any restraint during welding operations is reduced to a minimum.
10.1.3 Where primers
are applied over areas which will subsequently be welded, they are
to be of a quality accepted by LR as having no significant deleterious
effect on the finished weld.
10.1.4 Tack welding
should be kept to a minimum and, where used is to be equal in quality
to the finished welds. Tack welds should normally be removed before
completing the weld unless otherwise agreed and without damage to
the pipe.
10.1.5 The proposals
for NDE procedures are to be agreed with LR prior to the commencement
of construction.
10.1.6 All butt
welds are to be subjected to 100 per cent NDE by radiography is to
be to a standard acceptable to LR, for example BS 2910 — Methods
for Radiographic Examination of Fusion Welded Circumferential Butt
Joints in Steel Pipes, with acceptance criteria as detailed
in the construction code of BS 4515 — Specification for
Process of Welding of Steel Pipelines on Land and Offshore,
if not specified in the Code, proposals for examination by ultrasonics
are to be submitted for review and acceptance.
10.1.7 All defective
sections of welds are to be cut out, carefully re-welded and re-examined.
10.1.8 All radiographs
of field butt welds are to be stored by the pipeline Owner for at
least 2 years following start up of the pipeline. Adequate care should
be taken to ensure that the radiographs do not deteriorate in storage.
10.1.9 Weld procedures
for repairs and alterations are to be qualified and approved by LR.