7.1.1 If
                                 the initial assessment confirms that the shipyard's quality arrangements
                                 are satisfactory, the Committee will issue Part 1 or Part 2 and Part
                                 1 of LR's Quality Assurance Approval Certificates as appropriate.
                                 Maintenance of approval will be subject to the provisions of Pt  3, Ch  15,  8 Maintenance of approval.
                                 
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              7.1.2 Approval
                                 by another organisation will not be accepted as sufficient evidence
                                 that the arrangements for hull construction comply with these requirements.