6.1.1 In
                                 the first instance applications for approval under this Scheme will
                                 be considered on the recommendation of the local Surveyors.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              6.1.2 After
                                 receipt and appraisal of the main quality documentation, an assessment
                                 of the shipyard is to be carried out by the Surveyors to examine all
                                 aspects of the Quality System applicable to hull construction.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              6.1.3 The
                                 Surveyors will review the quality arrangements proposed by the Shipbuilder
                                 at the shipyard. They may advise as to how the proposed Quality System
                                 might be improved and where it is considered inadequate, advise how
                                 it might be revised to be acceptable to LR.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              6.1.4 For
                                 assessment to Part 1 of the Scheme, the Surveyors will review the
                                 Quality System in association with the quality documentation and will
                                 check that all aspects of the System are established and in accordance
                                 with the requirements of Pt  3, Ch  15,  3 Particulars to be submitted.
                                 
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              6.1.5 For
                                 assessment of Part 2 of the Scheme, the Surveyors will confirm that
                                 the requirements given in Pt  3, Ch  15,  3 Particulars to be submitted have
                                 been fully implemented and are complied with by a detailed examination
                                 of work in progress and by confirming that workmanship and the quality
                                 level being consistently achieved are to their satisfaction.