2.2.1
Re-testing
of materials:
-
Check tests may be
required at the discretion of the Surveyor.
-
In general, the manufacturer’s
chemical analysis will be accepted but may be subject to occasional
independent checks if required by the Surveyor.
-
When mechanical check
tests are required, the specified tests are to be carried out using
calibrated machines which are maintained in a satisfactory and accurate
condition.
2.2.2
Rectification
of defects:
-
In all cases, the removal
of defects, and repair by welding where appropriate, are to be carried
out to the satisfaction of the Surveyor.
-
Surface imperfections
may be removed by mechanical means as agreed with the Surveyor. After
such treatment, the dimensions are to comply with an agreed National
or International Standard and the area is to be proved free from defects.
The work is to be completed to the satisfaction of the Surveyor.
-
For steel castings,
flame scarfing or arc-air gouging may be used, provided that pre-heating
is used where necessary, the surfaces of the resulting depression
are subsequently ground smooth and complete elimination of the defective
material is confirmed by adequate non-destructive examination.
-
Repair by welding is
not to be carried out without the agreement of the Surveyor. Agreement
of the Surveyor is to be obtained before the work is commenced.
-
The complete removal
of all defects is to be proved by suitable non-destructive examinations
and the area is to be suitably prepared for welding.
-
Welding is to be carried
out using a qualified and approved procedure which is to include the
selection of suitable welding consumables. Pre-heating and post-weld
heat treatment may be necessary due to the particular chemical composition
or dimensions of the weld repairs. The repairs are to be carried out
by qualified welders under adequate supervision.
2.2.3
Fabrication:
-
All standards related
to weld procedures, qualification of welders, non-destructive test
procedures, non-destructive test personnel qualifications and non-destructive
acceptance criteria are to be agreed prior to the commencement of
work.
-
Welding procedures
are to be in accordance with the Rules for Materials or an agreed
National or International Standard. All welding procedures are to
be qualified by testing and be approved by the Surveyor.
-
Welding consumables
are to be of a type approved by LR. A list of currently approved welding
consumables is published in the Class Direct section of LR’s
website at http://www.lr.org/.
-
All welders are to
be qualified to the satisfaction of the Surveyor in accordance with
the Rules for Materials or other equivalent National or International
Standard.
-
Post-weld heat treatment
is to be applied under the following conditions:
-
For steels with nominal
yield strength below 420 N/mm2 where the as-welded hardness
exceeds 350 Hv.
-
For steels with
yield strength between 420 N/mm2 and 690 N/mm2 where
the as-welded hardness exceeds 420 Hv.
-
Welding of steel
castings where the thickness of the casting at the weld exceeds 30
mm.
-
Where weld thickness
exceeds 65 mm.
Post-weld heat treatment may be omitted
where the risk of fracture is demonstrated to be low or where the
consequences of fracture are demonstrated to be tolerable.
-
Following welding,
visual inspection is to be carried out by qualified inspectors to
ensure that welds are in accordance with the approved plan and comply
with agreed acceptance criteria. Surveyors will conduct visual examination
spot checks to confirm the overall quality of the welds against the
approved plans and agreed acceptance criteria.
-
In addition to visual
checks, welds are to be non-destructively examined to verify their
soundness. All non-destructive examinations (NDE) are to be carried
out to a written procedure that is representative of the item under
inspection and they are to be based upon a National or International
Standard. Personnel carrying out non-destructive examination or interpreting
the results of non-destructive examination are to be qualified to
the appropriate level of a nationally recognised scheme such as ISO
9712, EN 473, PCN, ACCP or SNT-TC-1A. Level 1 personnel are not permitted
to interpret results to Codes or Standards.
-
The extent of NDE is
to be in accordance with Table 12.3.1 Minimum requirements for
NDE in
Chapter 12.
-
The verification of
dimensional compliance to approved drawings is to be verified by the
Surveyor after machining and/or welding operations.