1.2.1 In the
first instance, and before work is commenced, the Surveyors are to
be satisfied that the required quality of welding is attainable with
the proposed welding plant, equipment and procedures reference is
made to the Materials and Qualification Procedures for Ships,
Book A, Procedure 0-4.
1.2.2 All welding
is to be in accordance with the requirements specified in Ch 13 Requirements for Welded Construction of the Rules for the Manufacture,
Testing and Certification of Materials (hereinafter referred
to as the Rules for Materials).