2.2.1 The level of rigor in verification is to be commensurate with the safety
criticality of the systems, equipment and components categorised in accordance with
the requirements of the Submarine Safety Assurance System.
2.2.2 Verification activities carried out independently by LR may include independent
analysis, design review, audit, survey, inspection and testing as appropriate for
the submarine lifecycle phase and requirements to be verified.
2.2.3 Verification activities carried out independently by LR are not a substitute for
second party verification carried out by the submarine designer, builder, or
maintenance organisation.