8.1 Verify that the following documentation is
on board in a suitable format:
-
.1 a copy of the Type Approval Certificate of
BWMS;
-
.2 a statement from the Administration, or from
a laboratory authorized by the Administration, to confirm that the
electrical and electronic components of the BWMS have been type-tested
in accordance with the specifications for environmental testing contained
in Part 3 of the annex;
-
.3 equipment manuals for major components of the
BWMS;
-
.4 an operations and technical manual for the
BWMS specific to the ship and approved by the Administration, containing
a technical description of the BWMS, operational and maintenance procedures,
and backup procedures in case of equipment malfunction;
-
.5 installation specifications;
-
.6 installation commissioning procedures; and
-
.7 initial calibration procedures.
8.2 Verify that:
-
.1 the BWMS installation has been carried out
in accordance with the technical installation specification referred
to in paragraph 8.1.5;
-
.2 the BWMS is in conformity with the Type Approval
Certificate of BWMS issued by the Administration or its representative;
-
.3 the installation of the complete BWMS has been
carried out in accordance with the manufacturer’s equipment
specification;
-
.4 any operational inlets and outlets are located
in the positions indicated on the drawing of the pumping and piping
arrangements;
-
.5 the workmanship of the installation is satisfactory
and, in particular, that any bulkhead penetrations or penetrations
of the ballast system piping are to the relevant approved standards;
and
-
.6 the control and monitoring equipment operates
correctly.