1.7 The Programme for prototype ballast water
treatment technologies in accordance with these Guidelines should
contain the following three main steps:
-
.1
Programme Application, Submission and
Approval: The submission should include a detailed plan describing
the prototype technology and implementation of the programme as described
in Section 3. Further, the applicant should include evidence on the
potential of the prototype technologies meeting or exceeding the performance
standard in regulation D-2. If the
prototype ballast water treatment technology makes use of Active Substances,
or preparations containing one or more Active Substances, the substances
should have received Basic Approval, as described by the Procedure
for the Approval of Ballast Water Management systems that make use
of Active Substances (G9). All of the above information should be
the basis for the Administration in its evaluation and approval of
the submitted programme. In the case where a programme is approved,
the applicant may proceed in accordance with the approved programme
taking into account any conditions set by the Administration.
-
.2
Installation Survey and Statement of
Compliance: The installation of the prototype ballast water
treatment technology in accordance with the approved Programme should
be verified by an installation survey. Provided that this survey confirms
adherence to the approved programme, including any applicable conditions
set by the Administration, a Statement of Compliance under regulation D-4 may be issued by the Administration.
-
.3
Performance Evaluations and Reporting: During
the test and evaluation period, a prototype ballast water treatment
technology should be subjected to on-going experimental testing and
evaluation according to the approved programme to evaluate both the
engineering and biological performance under shipboard operating conditions.
Reporting to the Administration should be of the form and schedule
in accordance with the approved programme.