6.1.1 To ensure compliance with this Standard,
the following shall be carried out by the qualified coating inspectors
certified to NACE Level II, FROSIO level Red or equivalent as verified
by the Administration or the recognized organization.
6.1.2 Coating inspectors shall inspect surface
preparation and coating application during the coating process by
carrying out, as a minimum, those inspection items identified in section
6.2 to ensure compliance with this Standard. Emphasis shall be placed
on initiation of each stage of surface preparation and coatings application
as improper work is extremely difficult to correct later in the coating
progress. Representative structural members shall be non-destructively
examined for coating thickness. The inspector shall verify that appropriate
collective measures have been carried out.
6.1.3 Results from the inspection shall be recorded
by the inspector and shall be included in the CTF (refer to annex
2, Example of Daily Log and Non-conformity Report).