Construction stage
|
|
Inspection items
|
Primary surface
preparation
|
1
|
The surface temperature of steel, the
relative humidity and the dew point shall be measured and recorded before
the blasting process starts and at times of sudden changes in
weather.
|
2
|
The surface of steel plates shall be
tested for soluble salt checked for oil, grease and other
contamination.
|
3
|
The cleanliness of the steel surface
shall be monitored in the shop primer application process.
|
4
|
The shop primer material shall be
confirmed to meet the requirements of 2.3 of table 1.
|
Thickness
|
|
If compatibility with the main
coating system has been declared, then the thickness and curing of the zinc
silicate shop primer to be confirmed to conform to the specified
values.
|
Block assembly
|
1
|
After completing construction of the
block and before secondary surface preparation starts, a visual inspection
for steel surface treatment including edge treatment shall be carried
out.
|
Any oil, grease or other visible
contamination to be removed.
|
2
|
After blasting/grinding/cleaning and
prior to coating, a visual inspection of the prepared surface shall be
carried out.
|
On completion of blasting and
cleaning and prior to the application of the first coat of the system, the
steel surface shall be tested for levels of remaining soluble salts in at
least one location per block.
|
3
|
The surface temperature, the relative
humidity and the dew point shall be monitored and recorded during the
coating application and curing.
|
4
|
Inspection to be performed of the
steps in the coating application process mentioned in table 1.
|
5
|
DFT measurements shall be taken to
prove that the coating has been applied to the thickness as specified and
outlined in annex 3.
|
Erection
|
1
|
Visual inspection for steel surface
condition, surface preparation and verification of conformance to other
requirements in Table 1, and the agreed specification to be
performed.
|
2
|
The surface temperature, the relative
humidity and the dew point shall be measured and recorded before coating
starts and regularly during the coating process.
|
3
|
Inspection to be performed of the
steps in the coating application process mentioned in table 1.
|