|
1
|
LIFTING
|
| The container, having the
prescribed internal loading, shall be lifted in such a way that no
significant acceleration forces are applied. After lifting, the container
shall be suspended or supported for five minutes and then lowered to the
ground.
|
|
(A)
|
Lifting from corner fittings
|
| TEST LOAD AND APPLIED FORCES
|
TEST PROCEDURES
|
|
Internal load:
|
(i)
Lifting from top corner fittings:
|
| A uniformly distributed load such that the sum of the mass of
container and test load is equal to 2R. In the case of a tank container,
when the test load of the internal load plus the tare is less than 2R, a
supplementary load, distributed over the length of the tank, is to be added
to the container.
|
Containers greater than 3,000 mm (to ft) (nominal) in length shall have
lifting forces applied vertically at all four top corner fittings.
|
| Containers of 3,000 mm (10ft) (nominal) in length or less shall have
lifting forces applied at all four top corner fittings, in such a way that
the angle between each lifting device and the vertical shall be 30°.
|
|
Externally applied forces:
|
(ii)
Lifting from bottom corner fittings:
|
| Such as to lift the sum of a mass of 2R in the manner prescribed
(under the heading TEST PROCEDURES).
|
Containers shall have lifting forces applied in such a manner that the
lifting devices bear on the bottom corner fittings only. The lifting forces
shall be applied at angles to the horizontal of:
|
|
|
30° for
containers of length 12,000 mm (40 ft) (nominal) or greater,
|
|
|
37° for containers of length 9,000 mm (30 ft) (nominal) and up to
but not including 12,000 mm (40 ft) (nominal),
|
|
|
45° for
containers of length 6,000 mm (20 ft) (nominal) and up to but not including
9,000 mm (30 ft) (nominal),
|
|
|
60° for
containers of length less than 6,000 mm (20 ft) (nominal).
|
|
(B)
|
Lifting by any other additional methods
|
| TEST LOAD AND APPLIED FORCES
|
TEST PROCEDURES
|
|
Internal load:
|
(i) Lifting from fork-lift pockets:
|
| A uniformly distributed load such that the sum of the mass of
container and test load is equal to 1.25R.
|
The container shall be placed on bars which are in the same
horizontal plane, one bar being centred within each fork-lift pocket which
is used for lifting the loaded container. The bars shall be of the same
width as the forks intended to be used in the handling, and shall project
into the fork pocket 75% of the length of the fork pocket.
|
|
Externally applied forces:
|
| Such as to lift the combined weight of 1.25R in the manner
prescribed (under the heading TEST PROCEDURES).
|
|
Internal load:
|
(ii) Lifting from grappler-arm positions:
|
| A uniformly distributed load such that the sum of the mass of
container and test load is equal to 1.25R. In the case of a tank container,
when the test load of the internal load plus the tare is less than 1.25R, a
supplementary load, distributed over the length of the tank, is to be added
to the container.
|
The container shall be placed on pads in the same horizontal
plane, one under each grappler-arm position. These pads shall be of the same
sizes as the lifting area of the grappler arms intended to be used.
|
|
Externally applied forces:
|
|
|
|
|
| Such as to lift the sum of a mass of 1.25R in the manner
prescribed (under the heading TEST PROCEDURES).
|
|
|
|
|
|
|
|
|
|
(iii) Other methods:
|
|
|
|
|
|
Where containers are designed to be lifted in the loaded
condition by any method not mentioned in (A) or (B)(i) and (ii) they shall
also be tested with the internal load and externally applied forces
representative of the acceleration conditions appropriate to that
method.
|