1.1.1 For ships operating on the Engine Special Survey cycle, the Chief Engineer or Operator
should arrange for Lloyd’s Register's Surveyors to carry out the Complete Survey of
machinery, where all machinery items are to be opened for survey, at five-year intervals.
1.1.3 Chief Engineers may not credit machinery items in LR Class Direct.
1.1.4 Machinery items should be opened out for inspection, as requested by the attending
Surveyor.
1.1.5 The Chief Engineer’s maintenance and monitoring records should be made available.
1.1.6 The Surveyor will ‘X’ Credit all items, subject to examination and testing, at the Complete
Survey of machinery.
NOTES:
- The procedures for examination of surveyable machinery items by Chief Engineers do not
apply to ships on Engine Special Survey.
- The Complete Survey of machinery should be harmonised with the Classification Special
Survey and Bottom Survey, whenever practicable.