1 The Maritime Safety Committee's attention was
earlier drawn to deficiencies in the loadings given in tables I and II of section 1 of part C in chapter
VI of the 1974 SOLAS Convention, and authorized the issue of MSC/Circ.310
which circular indicated that tables
I and II were only suitable
for divisions where the height of grain did not exceed 3 m and gave
guidance for grain heights in excess of 3 m.
2 Subsequent discussion has indicated, however,
that tables I and II may be used for determining the
load on grain divisions for grain heights of up to 6 m. The tables,
in SI units, are attached.
3 For heights of grain in excess of 6 m, the tables
of P/h2, as given herein, may be used as guidance in determining
the load on a division. Administrations should be guided by established
engineering practice when deriving the scantlings of high temporary
divisions.
4 For clarification, an example of the use of the tables of P/h2 is given hereunder:
-
To find Force (P) for a transverse division where h = 9.00
m
-
L/h = 2. From table II.
L, P/h2 = 1846.
-
Force (P) = 1846 x 9.02 = 149526 kN/m.
5 MSC/Circ.310 and Corr.1 is hereby revoked.