Construction stage
|
|
Inspection items
|
Primary surface
preparation
|
1
|
The surface temperature of steel, the
relative humidity and the dew point shall be measured and recorded before the
blasting process starts and at times of sudden changes in weather.
|
2
|
The surface of steel plates shall be
tested for soluble salt checked for oil, grease and other
contamination.
|
3
|
The cleanliness of the steel surface
shall be monitored in the shop primer application process.
|
4
|
The shop primer material shall be
confirmed to meet the requirements of 2.3 of table 1. Verified by manufacturer.
|
Thickness
|
|
If compatibility with the main coating
system has been declared, then the thickness and curing of the zinc silicate
shop primer to be confirmed to conform to the specified values.
|
Block assembly
|
1
|
After completing construction of the
block and before secondary surface preparation starts, a visual inspection for
steel surface treatment including edge treatment shall be carried out.
|
Any oil, grease or other visible
contamination to be removed.
|
2
|
After blasting/grinding/cleaning and
prior to coating, a visual inspection of the prepared surface shall be carried
out.
|
On completion of blasting and cleaning
and prior to the application of the first coat of the system, the steel surface
shall be tested for levels of remaining soluble salts in at least one location
per block.
|
3
|
The surface temperature, the relative
humidity and the dew point shall be monitored and recorded during the coating
application and curing.
|
4
|
Inspection to be performed of the steps
in the coating application process mentioned in table 1.
|
5
|
DFT measurements shall be taken to prove
that the coating has been applied to the thickness as specified.
|
Erection
|
1
|
Visual inspection for steel surface
condition, surface preparation and verification of conformance to other
requirements in table 1, and the agreed specification to be performed.
|
2
|
The surface temperature, the relative
humidity and the dew point shall be measured and recorded before coating starts
and regularly during the coating process.
|
3
|
Inspection to be performed of the steps
in the coating application process mentioned in table 1.
|