14.7.1 Transfer operations, including the weights
of the loads to be handled and emergency procedures, should be discussed
and agreed between personnel on the unit and on attending vessels
prior to commencement of such transfers. Direct communication should
be maintained with the crane operator throughout such operations.
14.7.2 The unit should be equipped with at least
two independent means for mooring attending vessels. The mooring position
should be such that sufficient crane capacity (lifting and outreach)
is available to handle loads in a safe manner.
14.7.3 The arrangement of mooring connexions on
the unit to facilitate transfer operations should have regard to the
risk of damage should the attending vessel come in contact with the
unit.
14.7.4 The mooring lines between the unit and
the attending vessel should, as far as practicable, be arranged so
that if a line breaks, danger to personnel on both the attending vessel
and the unit is minimized.
14.7.5 Discharges from the unit, such as those
from the sewage system or ventilation from bulk tanks, should be arranged
so that they minimize danger to personnel on the deck of attending
vessels.