4.1 Following approval of the Programme Application,
the Programme may proceed to installing the onboard prototype ballast
water treatment technology.
4.2 Following installation a survey should be
performed by the Administration, or any designated body appointed
by the Administration to act on its behalf, to verify that the system
installation has been carried out in accordance with the approved
Programme and that the workmanship of the installation is satisfactory.