5 To bring into line the performance of SSASs,
these should be tested as follows:
-
.1 ships constructed before 1 July 2006, not later
than the first survey of the radio installation on or after 1 July
2006; and
-
.2 ships constructed on or after 1 July 2006,
before the ship enters service;
to verify that, when the SSAS is activated, the information
specified in paragraph 3 above and the indication that the security
of the ship is under threat or it has been compromised are received
by the designated recipient. However, if the arrangements established
by the Administration are in compliance with paragraph 3 above such
additional tests are not required.