6.6.1.1 Inspection and non-destructive testing
of welds shall be in accordance with the requirements of 6.5.5 and
6.5.6. Where higher standards or tolerances are assumed in the design,
they shall also be satisfied.
6.6.2.1 For type C tanks and type B tanks primarily
constructed of bodies of revolution, the tolerances relating to manufacture,
such as out-of-roundness, local deviations from the true form, welded
joints alignment and tapering of plates having different thicknesses,
shall comply with recognized standards. The tolerances shall also
be related to the buckling analysis referred to in 4.22.3.2 and 4.23.3.2.
6.6.2.2 For type C tanks of carbon and carbon-manganese
steel, post-weld heat treatment shall be performed after welding,
if the design temperature is below -10°C. Post-weld heat treatment
in all other cases and for materials other than those mentioned above
shall be to recognized standards. The soaking temperature and holding
time shall be to the recognized standards.
6.6.2.3 In the case of type C tanks and large
cargo pressure vessels of carbon or carbon-manganese steel, for which
it is difficult to perform the heat treatment, mechanical stress relieving
by pressurizing may be carried out as an alternative to the heat treatment
and subject to the following conditions:
-
.1 complicated welded pressure vessel parts such
as sumps or domes with nozzles, with adjacent shell plates shall be
heat treated before they are welded to larger parts of the pressure
vessel;
-
.2 the mechanical stress relieving process shall
preferably be carried out during the hydrostatic pressure test required
by 4.23.6, by applying a higher pressure than the test pressure required
by 4.23.6.1. The pressurizing medium shall be water;
-
.3 for the water temperature, 4.23.6.2 applies;
-
.4 stress relieving shall be performed while the
tank is supported by its regular saddles or supporting structure or,
when stress relieving cannot be carried out on board, in a manner
which will give the same stresses and stress distribution as when
supported by its regular saddles or supporting structure;
-
.5 the maximum stress relieving pressure shall
be held for 2 h per 25 mm of thickness, but in no case less than 2
h;
-
.6 the upper limits placed on the calculated stress
levels during stress relieving shall be the following:
-
.1 equivalent general primary membrane stress:
0.9 Re
;
-
.2 equivalent stress composed of primary bending
stress plus membrane stress: 1.35 Re
, where Re
is the specific lower minimum yield stress or
0.2% proof stress at test temperature of the steel used for the tank;
-
.7 strain measurements will normally be required
to prove these limits for at least the first tank of a series of identical
tanks built consecutively. The location of strain gauges shall be
included in the mechanical stress relieving procedure to be submitted
in accordance with 6.6.2.3;
-
.8 the test procedure shall demonstrate that a
linear relationship between pressure and strain is achieved at the
end of the stress relieving process when the pressure is raised again
up to the design pressure;
-
.9 high-stress areas in way of geometrical discontinuities
such as nozzles and other openings shall be checked for cracks by
dye penetrant or magnetic particle inspection after mechanical stress
relieving. Particular attention in this respect shall be paid to plates
exceeding 30 mm in thickness;
-
.10 steels which have a ratio of yield stress
to ultimate tensile strength greater than 0.8 shall generally not
be mechanically stress relieved. If, however, the yield stress is
raised by a method giving high ductility of the steel, slightly higher
rates may be accepted upon consideration in each case;
-
.11 mechanical stress relieving cannot be substituted
for heat treatment of cold formed parts of tanks, if the degree of
cold forming exceeds the limit above which heat treatment is required;
-
.12 the thickness of the shell and heads of the
tank shall not exceed 40 mm. Higher thicknesses may be accepted for
parts which are thermally stress relieved;
-
.13 local buckling shall be guarded against, particularly
when tori-spherical heads are used for tanks and domes; and
-
.14 the procedure for mechanical stress relieving
shall be to a recognized standard.
During construction, the requirements for testing and inspection
of secondary barriers shall be approved or accepted by the Administration
or recognized organization acting on its behalf (see 4.6.2.5 and 4.6.2.6).
6.6.4
Semi-membrane tanks
For semi-membrane tanks, the relevant requirements in section
6.6 for independent tanks or for membrane tanks shall be applied as
appropriate.
The quality assurance/quality control programme shall ensure
the continued conformity of the weld procedure qualification, design
details, materials, construction, inspection and production testing
of components. These standards and procedures shall be developed during
the prototype testing programme.