Statutory Documents - IMO Publications and Documents - Resolutions - Marine Environment Protection Committee - Resolution MEPC.197(62) – 2011 Guidelines for the Development of the Inventory of Hazardous Materials – (Adopted on 15 July 2011) - Annex – 2011 Guidelines for the Development of the Inventory of Hazardous Materials - Appendix 5 – Example of the Development Process for Part I of the Inventory for Existing Ships - 6 Step 5: Preparation of Part I of the Inventory and related documentation

6 Step 5: Preparation of Part I of the Inventory and related documentation

6.1 Development of Part I of the Inventory

 The results of the check and the estimated quantity of Hazardous Materials should be recorded on the checklist. Part I of the Inventory should be developed with reference to the checklist

6.2 Development of location diagram of Hazardous Materials

 With respect to Part I of the Inventory, the development of a location diagram of Hazardous Materials is recommended in order to help the Ship Recycling Facility gain a visual understanding of the Inventory.

Checklist (Step 4 and Step 5) Analysis and Definition of Scope of Assessment for "Sample Ship"

Example of the Inventory for existing ships

Inventory of Hazardous Materials: "Sample Ship"

Part I – Hazardous Materials Contained in the Ship's Structure and Equipment

I-1 Paints and coating systems containing materials listed in Table A and Table B of appendix 1 of the Guidelines

No. Application of paint Name of paint Location footnote Materials (classification in appendix 1) Approx. quantity Remarks
1 AF paint Unknown paints Flat bottom TBT 60.00 kg Confirmed by sampling
2            
3            

I-2 Equipment and machinery containing materials listed in Table A and Table B of appendix 1 of the Guidelines

No. Name of equipment and machinery Locationfootnote Materials (classification in appendix 1) Parts where used Approx. quantity Remarks
1 Main engine Lower floor Asbestos Exh. pipe packing 3.50 kg  
2 Aux. boiler 3rd deck Asbestos Unknown packing 10.00 kg PCHM (potentially containing Hazardous Material)
3 Piping/flange Engine-room Asbestos Packing 50.00 kg PCHM
4 Ref. provision plant 2nd deck HCFC Refrigerant (R22) 20.00 kg  
5 Batteries Navig. Bridge deck Lead   96.00 kg  
             

I-3 Structure and hull containing materials listed in Table A and Table B of appendix 1 of the Guidelines

No. Name of structural element Location footnote Materials (classification in appendix 1) Parts where used Approx. quantity Remarks
1 Back deck ceiling Upper deck Asbestos Engine-room ceiling (A class) 3.80 kg Confirmed by sampling
2            
3            

Example of location diagram of Hazardous Materials


Copyright 2016 Clasification Society, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasification Society, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasification Society'. Clasification Society Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasification Society entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.