3 Method of Test
3.1 Principle
This test procedure is intended for the determination of
the effectiveness of different aerosol agent extinguishing systems
against spray fires, pool fires and class A fires. It also establishes
the minimum safe distances from condensed aerosol generators to personnel
and combustible materials.
3.2 Apparatus
3.2.1
Test room
The tests should be performed in 100 m2 room,
with no horizontal dimension less than 8 m, with a ceiling height
of 5 m. The test room should be provided with a closable access door
measuring approximately 4 m2 in area. In addition, closable
ventilation hatches measuring at least 6 m2 in total area
should be located in the ceiling. A larger room may be employed if
approvals are sought for larger volumes.
3.2.2
Integrity of test enclosure
The test enclosure should be nominally leaktight when doors
and hatches are closed. The integrity of seals on doors, hatches and
other penetrations (e.g., instrumentation access ports) should be
verified before each test.
3.2.3
Engine mock-up
3.2.3.1 An engine mock-up of size (width x length
x height) 1 m x 3 m x 3 m should be constructed of sheet steel with
a nominal thickness of 5 mm. The mock-up should be fitted with two
steel tubes diameter 0.3 m and 3 m length that simulate exhaust manifolds
and a solid steel plate. At the top of the mock-up, a 3 m2 tray
should be arranged (see figures 1, 2 and 3).
3.2.3.2 A floor plate system 4 m x 6 m x 0.75
m high should surround the mock-up. Provision should be made for placement
of the fuel trays, as described in table 1, and located as described
in table 2.
3.2.4
Instrumentation
Instrumentation for the continuous measurement and recording
of test conditions should be employed. The following measurements
should be made:
-
.1 temperature of the generator casing;
-
.2 temperature of the generator discharge stream
measured at 0.5 m, 1.0 m and 2.0 m away from the discharge ports;
-
.3 temperature at three vertical positions (e.g.,
1 m, 2.5 m and 4.5 m);
-
.4 enclosure pressure;
-
.5 gas sampling and analysis, at mid-room height,
for oxygen, carbon dioxide, carbon monoxide and other relevant products;
-
.6 means of determining flame-out indicators;
-
.7 fuel nozzle pressure in the case of spray fires;
-
.8 fuel flow rate in the case of spray fires;
-
.9 discharge nozzle pressure; and
-
.10 means of determining generator discharge duration.
3.2.5
Generators/nozzles
3.2.5.1 For test purposes, generators/nozzles
should be located as recommended by the manufacturer.
3.2.5.2 If more than one generator/nozzle is used,
they should be symmetrically located.
3.2.6
Enclosure temperature
The ambient temperature of the test enclosure at the start
of the test should be noted and serve as the basis for calculating
the concentration that the agent would be expected to achieve at that
temperature and with that agent weight applied in the test volume.
3.3 Test fires and programme
3.3.1
Fire types
The test programme, as described in table 3, should employ
test fires as described in table 1 below.
Parameters of test
fibres
|
Fire
|
Type
|
Fyeahuel
|
Fire size, MW
|
Remarks
|
|
A
|
76 − 100 mm ID
can
|
Heptane
|
0.0012 to
0.002
|
Tell
tale
|
|
B
|
0.25
m2 tray
|
Heptane
|
0.35
|
(See Note
1)
|
|
C
|
2 m2
tray
|
Diesel/fuel
oil
|
3
|
(See Note
1)
|
|
D
|
4 m2
tray
|
Diesel/fuel
oil
|
6
|
|
|
E
|
Low pressure,
low flow spray
|
Heptane
0.03 ± 0.005 kg/s
|
1.1
|
|
|
F
|
Wood
crib
|
Spruce or
fir
|
0.3
|
(See Note
2)
|
|
G
|
0.10 m2
tray
|
Heptane
|
0.14
|
|
|
H
|
Polymeric
sheets
|
PMMA,
Polypropylene, ABS
|
|
(See Note
3)
|
|
Notes to table 1:
|
|
|
|
1 |
= |
Diesel/Fuel oil means light diesel or
commercial fuel oil.
|
|
|
|
|
2 |
= |
The wood crib should be substantially the same
as described in standard ISO 14520-1:2006 (Gaseous fire
extinguishing systems, Physical properties and system
design, Part 1: General Requirements). The crib should
consist of six members of trade size 50 mm x 50 mm x 450
mm, kiln dried spruce or fir lumber having a moisture
content between 9 and 13%. The members should be placed in
4 alternate layers at right angles to one another. Members
should be evenly spaced forming a square structure.
Ignition of the crib should be achieved by burning
commercial grade heptane in a square steel tray 0.25
m2 in area. During the pre-burn period the
crib should be placed centrally above the top of the tray
a distance of 300 to 600 mm.
|
|
|
|
|
3 |
= |
The polymeric sheet test should be
substantially the same as described in standard ISO
14520-1:2006 (Gaseous fire extinguishing systems, Physical
properties and system design, Part 1: General
Requirements).
|
|
Spray fire test
parameters
|
Fire type
|
Low pressure, low flow (E)
|
|
Spray nozzle
|
Wide spray angle
(80°) full cone type
|
|
Nominal fuel pressure
|
8.5 Bar
|
|
Fuel flow
|
0.03 + 0.005 kg/s
|
|
Fuel temperature
|
20 + 5°C
|
|
Nominal heat release rate
|
1.1 + 0.1 MW
|
3.3.2
Test programme
3.3.2.1 The fire test programme should employ
test fires singly or in combination, as outlined in table 3 below.
Test programme
|
Test No.
|
Fire combinations (see table 1)
|
|
1
|
|
A: |
= |
Tell tales, 8 corners. (see note)
|
|
|
2
|
|
B: |
= |
0.25 m2 heptane tray under mock-up
|
|
G: |
= |
0.10 m2 heptane tray on deck plate
located below solid steel obstruction plate
|
|
|
= |
Total fire load: 0.49 MW
|
|
|
3
|
|
C: |
= |
2 m2 diesel/fuel oil tray on deck plate
located below solid steel obstruction plate
|
|
F: |
= |
Wood crib positioned as in figure 1
|
|
E: |
= |
Low pressure, low flow horizontal spray −
concealed − with impingement on inside of engine mock-up
wall.
|
|
H |
= |
Polymeric sheets positioned as in figure
1
|
|
|
= |
Total fire load: 4.4 MW
|
|
|
4
|
|
D: |
= |
4 m2 diesel tray under engine
mock-up
|
|
|
= |
Total fire load: 6 MW
|
|
| Note to table 3:
|
|
1 |
= |
Tell-tale fire cans should be located as
follows:
|
|
.1 |
= |
in upper corners of enclosure 150 mm below
ceiling and 50 mm from each wall; and
|
|
.2 |
= |
in corners on floors 50 mm from walls.
|
|
3.3.2.2 All applicable tests of table 3 should
be conducted for every new fire-extinguishing media.
3.3.2.3 Only test 1 is required to evaluate new
nozzles and related distribution system equipment (hardware) for systems
employing fire-extinguishing media that have successfully completed
the requirements of paragraph 3.3.2.2 above. Test 1 should be conducted
to establish and verify the manufacturer’s minimum nozzle design
pressure.
3.4 Extinguishing system
3.4.1
System installation
The extinguishing system should be installed according to
the manufacturer’s design and installation instructions. The
maximum vertical distance should be limited to 5 m.
3.4.2
Agent
3.4.2.1 Design application density
The agent design application density is the net mass of
agent per unit volume (g/m3) required by the system designer
for the fire protection application.
The test density of agent to be used in the fire-extinguishing
tests should be the design application density specified by the manufacturer,
except for test 1, which should be conducted at not more than 77%
of the manufacturer’s recommended design application density.
3.4.2.3 Quantity of aerosol agent
The quantity of aerosol agent to be used should be determined
as follows:
|
W
|
= |
|
where:
|
W |
= |
agent mass (g); |
|
V |
= |
volume of test
enclosure (m3);
|
|
q |
= |
design application
density (g/m3); and
|
|
f |
= |
efficiency coefficient
of the manufacturer’s generator (%) |
3.5 Procedure
3.5.1
Fuel levels in trays
The trays used in the test should be filled with at least
30 mm fuel on a water base. Freeboard should be 150 ± 10 mm.
3.5.2
Fuel flow and pressure measurements
For spray fires, the fuel flow and pressure should be measured
before and during each test.
3.5.3
Ventilation
3.5.3.1 Pre-burn period
During the pre-burn period the test enclosure should be well
ventilated. The oxygen concentration, as measured at mid-room height,
should not be less than 20% volume at the time of system discharge.
3.5.3.2 End of pre-burn period
Doors, ceiling hatches and other ventilation openings should
be closed at the end of the pre-burn period.
3.5.4
Duration of test
3.5.4.1 Pre-burn time
Fires should be ignited such that the following burning times
occur before the start of agent discharge:
-
.1 sprays − 5 to 15 s;
-
.2 trays − 2 min;
-
.3 crib – 3 separate tests, one of 2 min,
one of 4 min and one of 6 min; and
-
.4 polymeric sheets – 210 s.
3.5.4.2 Discharge time
Aerosol agents should be discharged at a rate sufficient to
achieve 100% of the minimum design density in 120 s or less.
3.5.4.3 Hold time
After the end of agent discharge the test enclosure should be
kept closed for 15 min.
3.5.5
Measurements and observations
3.5.5.1 Before test:
-
.1 temperature of test enclosure, fuel and engine
mock-up;
-
.2 initial weights of agent containers;
-
.3 verification of integrity agent distribution
system and nozzles; and
-
.4 initial weight of wood crib.
3.5.5.2 During test:
-
.1 start of the ignition procedure;
-
.2 start of the test (ignition);
-
.3 time when ventilating openings are closed;
-
.4 time when the extinguishing system is activated;
-
.5 time from end of agent discharge;
-
.6 time when the fuel flow for the spray fire
is shut off;
-
.7 time when all fires are extinguished;
-
.8 time of re-ignition, if any, during hold time;
-
.9 time at end of hold time;
-
.10 at the start of test initiate continuous monitoring
as per paragraph 3.2.4 above; and
-
.11 for condensed aerosol generators:
3.5.6
Tolerances
Unless otherwise stated, the following tolerances should
apply:
| .1
|
length
|
± 2% of
value;
|
| .2
|
volume
|
± 5% of
value;
|
| .3
|
pressure
|
± 3% of
value;
|
| .4
|
temperature
|
± 5% of value;
and
|
| .5
|
concentration
|
± 5% of
value.
|
These tolerances are in accordance with standard ISO 6182-1:2004.
|
| Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
 |
|