12.1 The towing equipment should be designed according
to the below mentioned recommendations and recognized standards. The
towing arrangements should be suitable for the particular tow and
of adequate strength.
12.2 The towing vessel should be equipped with
a towing winch.
12.3 It is recommended that the towing winch brakes
should have an appropriate static holding capacity to that of the
documented minimum breaking load (MBL) of the largest towline to be
used. The holding capability should be calculated for the outermost
towline layer on the winch drum at which towing will be performed.
12.4 The design and scantling of the towing winch,
including supports, should be capable of withstanding the breaking
load of the main towing wire rope without permanent deformation.
12.5 It should be possible to release the tension
on the winch drum(s) in an emergency and in all operational modes.
The end attachment of the towing wire rope to the winch drum should
be of limited strength, thus forming a weak link in case the towline
has to be run out. After an emergency release the winch brakes should
revert to normal function without delay. It should also be possible
to carry out the emergency release sequence (emergency release/application
of brakes) even during a black-out.
12.6 It is recommended that on board towing vessels,
whenever practicable, the winch should be fitted with equipment for
measuring the tension in the towline. This equipment should, as a
minimum, record the mean tension and the tension peaks, and the information
should be displayed in the wheel house.
12.7 Means should be provided to spool the towline
effectively on the drum(s).
12.8 Towline protection sleeves, or other means
should be provided to prevent the towlines being damaged by chafing
or abrasion. There should be no sharp edges or obstructions at the
stern of the vessel that may damage the towlines during operation.
A sufficient number of spare towline sleeves should be carried on
board.
12.9 An appropriate length for the towline should
be determined using established criteria. Where no such criteria has
been established, the minimum required length (L) of the main towline
should be determined from the formula;
where:
|
BL |
= |
Documented breaking
load of the towline, |
|
BP |
= |
Continuous bollard
pull |
12.10 All wire ropes in use should have the same
lay (i.e. right hand, left hand, etc.).
12.11 The minimum documented breaking load (MBL)
of the main towline should generally be in accordance with the following
table:
| Bollard
pull (BP) (tonnes)
|
<40
|
40-90
|
>90
|
| MBL
(tonnes)
|
3.0xBP
|
(3.8-BP/50) BP
|
2.0xBP
|
12.12 A spare towline satisfying all requirements
for the main towline should be kept on board the towing vessel.
If the towing winch is equipped with two drums the spare towline
should preferably be stored on the winch drum, readily available for
use.
The alternative is to have a spare towline which
should be in position and so arranged to ensure that transfer to the
main towing drum is easily, quickly and safely effected.
In
case of two towed objects whereby two independent towlines (main and
spare) are to be connected, an extra spare towline should be on board,
arranged as specified above.
12.13 All wire rope terminations should be hard
eyes, i.e. reinforced thimbles or spelter sockets except for the end
connection to the drum on the towing winch.
12.14 All connecting items like shackles, rings,
etc., should have an ultimate load bearing capacity of minimum 50%
in excess of the documented minimum breaking load (MBL) of the towing
arrangement to be used.
12.15 If fibre rope pennants are used, the pennants
should be in a sound condition and the minimum breaking load of any
fibre rope pennants should not be less than:
- 2.0 times the tow line MBL, for tugs with bollard pull less than
50 tonnes;
- 1.5 times the tow line MBL, for tugs with bollard pull greater
than 100 tonnes; and
- linearly interpolated between 1.5 and 2.0 times the tow line MBL
for tugs with bollard pull between 50 and 100 tonnes.
Fibre rope pennants should be of grommet construction and be
terminated with hard eyes, and should not normally be connected directly
to the apex of the towing bridle.
12.16 The towing vessel should be equipped with
sufficient spare equipment to completely replicate the towing arrangements,
unless found impractical.
12.17 Inspection of the towline should be carried
out on completion of each towing operation. The results of the inspection
should always be recorded as a basis for decision on future inspection
programs. The inspection should also be noted on the towing log (Appendix B).
12.18 No part of any towline arrangement should
be used for the towing operation if:
- the reduction in cross sectional area due to wear, abrasion, corrosion
and broken wires exceeds 10% or there is severe kinking, crushing
or other damage resulting in distortion of the rope structure;
- end sockets or other towline terminations such as thimbles, etc.,
are damaged, deformed or significantly corroded.
12.19 If relevant, gog ropes or alternative arrangement
should be provided to prevent athwartship pull, and to facilitate
retrieving of the towline. The arrangement should be remotely operated
from a safe position. A spare gog rope should be carried on board.