4 Hopper Knuckle Connection
4.1 Design standard C to H
4.1.1
The welded knuckle between hopper plating and inner bottom plating for double-hull oil
tankers is to be designed according to the design standard C in Table 3. The design
standard D in Table 4 may be used as an alternative to increase fatigue strength at the
hopper connection.
4.1.2
The welded knuckle between hopper plating and inner bottom plating for bulk carriers is
to be designed according to the design standard E in Table 5.
4.1.3
The radiused knuckle between hopper plating and inner bottom plating is to be designed
according to the design standard F in Table 6 for double hull oil tankers.
Alternative structural arrangements may be accepted based on verification in accordance
with Ch 9, Sec 5, [3.3].
4.1.4
The radiused knuckle between hopper plating and inner bottom plating for bulk carriers is
to be designed according to the design standard G in Table 7.
4.1.5
The radiused knuckle between hopper plating and inner side plating for oil tankers and
double side bulk carriers is to be designed according to the design standard H in Table
8.
4.1.6
In general, the prescribed minimum requirements for welding, weld dressing and building
tolerances as given in Table 3 to Table 8 are to be followed. Alternative positioning
and/or dispensation of some support structure, such as transverse and longitudinal
brackets may be accepted subject to demonstration of acceptable fatigue lives. Inserts
and/or weld dressing additional to those prescribed may be required as a consequence of
hot spot fatigue analysis.
Table 2 : Design standard B – scallops in way of block joints
Welding of deck stiffeners in
way of block joints
|
Critical areas
|
Design standard B
|
|
|
|
|
Critical locations
|
|
|
Note 1: Alternative scallop geometry to
that shown in option II may be accepted subject to demonstration of
satisfactory fatigue life based on hull girder loads taking into account
additional stress concentration factor in way of weld
|
Critical location
|
Welding of deck stiffeners in way of block joints in
cargo tank region, the strength deck and side above 0.9 D from the
baseline.
|
Detail design standard
|
All scallops are to be fitted according to detail design
standard B.
|
Building tolerances
|
Ensure alignment of all structural members according to IACS
Recommendation No. 47.
|
Welding requirements
|
Full penetration butt weld, free of undercut or notches, around the
web and flange of the longitudinal stiffener at block joints,
particularly in way of the weld termination at the scallop for option
II.
|
Table 3 : Design standard C – hopper knuckle connection detail, welded, without
bracket, double hull oil tanker
Connections of floors in
double bottom tanks to hopper tanks Hopper corner connections employing
welded inner bottom and hopper sloping plating
|
Critical areas
|
Design standard C
|
|
|
Critical locations
|
|
Minimum requirement
|
As a minimum, detail design standard C or D is to be fitted. The
ground surface is to be protected by a stripe coat of suitable paint
composition, where the lower hopper knuckle region of cargo tanks is not
coated.
|
Critical location
|
Hopper sloping plating connections to inner bottom plating in way of
floors. Floor connections to inner bottom plating and side girder in way
of hopper corners.
|
Detail design
standard
|
Elimination of scallops in way of hopper corners, extension of inner
bottom plating to reduce level of resultant stresses arising from cyclic
external hydrodynamic pressure, cargo inertia pressure and hull girder
loads. Scarfing bracket thickness is to be close to that of the inner
bottom in way of the knuckle.
|
Building tolerances
|
Median line of hopper sloping plate is to be in line with the median
line of the girder with an allowable tolerance of
tas-built/3 or 5 mm, whichever is less, where
tas-built is the as-built side girder
thickness. The allowable tolerance is to be measured parallel to the
inner bottom.
|
Welding
requirements
|
Full or partial penetration welding is to be applied to
hopper sloping plating and inner bottom plating connection. Partial
penetration welding is to be applied to connections of side girder
to inner bottom plating, to connections of floors to inner bottom
plating and to side girder, to connections of hopper transverse webs
to sloping plating, to inner bottom and to side girder in way of the
hopper knuckle. Definition of full and partial penetration welding
and their required extent are given in Ch 12, Sec 3
Weld between hopper plating and inner bottom plating to be enlarged
and ground smooth. Visible undercuts are to be removed, see Ch 9,
Sec 3, [6].
Weld enlargement and grinding are applicable to minimum 200 mm on
each side of the floor.
|
Table 4 : Design standard D – hopper knuckle connection detail, welded, with
bracket, double hull oil tanker
Connections of floors in
double bottom tanks to hopper tanks Hopper corner connections employing
welded inner bottom and hopper sloping plating
|
Critical areas
|
Design standard D
|
|
Note 1: Bracket to be fitted
inside cargo tank.
Note 2: Bracket to extend
approximately to the first longitudinal.
Note 3:
The bracket toes are to have a soft nose design.
Note 4: Bracket material to be same as that of inner bottom.
Note 5: Slenderness of bracket to be in accordance with
Ch 8, Sec 2, [5.2].
|
Critical locations
|
|
Minimum requirement
|
As a minimum, detail design standard C or D is to be applied.
|
Critical location
|
Hopper sloping plating connections to inner bottom plating in way of
floors. Floor connections to inner bottom plating and side girder in way
of hopper corners. The bracket connection to inner bottom and hopper
sloping plate.
|
Detail design standard
|
Elimination of scallops in way of hopper corners, extension of inner
bottom plating to reduce level of resultant stresses arising from cyclic
external hydrodynamic pressure, cargo inertia pressure and hull girder
loads. Scarfing bracket thickness similar to that of the inner bottom in
way of the knuckle.
|
Building tolerances
|
Median line of hopper sloping plate is to be in line with the median
line of girder with an allowable tolerance of
tas-built /3 or 5 mm, whichever is less, where
tas-built is the as-built side girder
thickness.
|
Welding requirements
|
Partial penetration welding is to be applied to hopper sloping
plating and inner bottom plating connection, to connections of side
girder to inner bottom plating, to connections of floors to inner
bottom plating and to side girder, to connections of hopper
transverse webs to sloping plating, to inner bottom and to side
girder in way of the hopper knuckle.
Partial penetration welding is to be applied to the bracket
connections to inner bottom and hopper sloping plate, full
penetration welding is to be applied at bracket toes. Definition of
full and partial penetration welding and their required extent are
given in Ch 12, Sec 3.
|
Table 5 : Design standard E – hopper knuckle connection detail, welded, bulk
carrier
Connections of floors in
double bottom tanks to hopper tanks Welded knuckle connection of hopper
tank sloping plating to inner bottom plating
|
Critical areas
|
Design standard E
|
|
|
Critical locations
|
|
Minimum
requirement
|
As a minimum, detail design standard E is to be fitted.
Ballast holds: No scallops or close scallops with collars; scarfing
bracket; intermediate bracket if floor spacing greater than 2.5 m.
Dry holds: No scallop or close scallops with collars and scarfing
bracket.
|
Critical location
|
Hopper sloping plating connections to inner bottom plating in way of
the floors. Floor connections to inner bottom plating and side girder in
way of the hopper knuckle.
|
Detail design
standard
|
Elimination of scallops in way of hopper knuckle, extension of inner
bottom plating to reduce level of resultant stresses arising from cyclic
external hydrodynamic pressure, cargo inertia pressure and hull girder
loads. Scarfing bracket net thickness is to be minimum 80% of that of
the inner bottom in way of knuckle and steel material to be of the same
yield strength.
|
Building
tolerances
|
Median line of hopper sloping plate is to be in line with the median
line of girder with an allowable tolerance of
tas-built/3 or 5 mm, whichever is less,
where tas-built is the as-built side girder
thickness.
|
Welding
requirements
|
Full or partial penetration welding is to be applied to hopper
sloping plating and inner bottom plating connection for the length of
the cargo hold. Partial penetration welding is to be applied to
connections of side girder to inner bottom plating, to connections of
floors to inner bottom plating and to side girder, to connections of
hopper transverse webs to sloping plating, to inner bottom and to side
girder in way of the hopper knuckle. Weld between hopper plating and
inner bottom plating is to be enlarged and ground smooth. Visible
undercuts are to be removed. Weld enlargement and grinding are
applicable to minimum 200 mm on each side of the floor. Definition of
full and partial penetration welding and their required extent are given
in Ch 12, Sec 3.
|
Table 6 : Design standard F – hopper knuckle connection detail, radiused type,
for double hull oil tanker
Connections of floors in
double bottom tanks to hopper tanks Hopper corner connections employing
radiused knuckle between inner bottom and hopper sloping plating
|
Critical areas
|
Design standard F
|
|
|
Critical locations
|
|
Note 1: Distance from side
girder to centre of knuckle is to be as small as practicable, but is
not to exceed 50 mm.
Note 2: The knuckle radius
is not to be less than 4.5 tas-built or 100 mm,
whichever is the greater, where tas-built is the
as-built thickness of the knuckle part.
Note 3:
Additional transverse brackets offset at a suitable distance on
either side of transverse floor/hopper connection.
Note 4: Additional longitudinal bracket on the side of
sloping plate.
Note 5: Longitudinal and/or
transverse brackets may be omitted if it can be demonstrated that
the girder provides sufficient support at the knuckle line, i.e.
that fatigue requirements according to Ch 9, Sec 5 and local
strength analysis requirements according to Ch 7, Sec 3 are
fulfilled.
|
Critical location
|
Floor and hopper transverse web connections to inner bottom plating
and hopper sloping plate, respectively and to side girder in way of
hopper knuckle. Side girder connections to inner bottom plating in way
of floors.
|
Detail design standard
|
Elimination of scallops in way of hopper/girder connection and
additional transverse and longitudinal brackets to reduce peak and range
of resultant stresses arising from cyclic external hydrodynamic
pressure, cargo inertia pressure, and hull girder global loading, and
provide additional support to sloping plate.
|
Building tolerances
|
The nominal distance between the centres of thickness of the two
abutting members (e.g. floor and hopper web plate) is not to exceed 1/3
of the as-built thickness of the side girder.
|
Welding requirements
|
Full penetration welding is to be applied to connections of floors to
hopper/inner bottom plating in way of radiused hopper knuckle. Partial
penetration welding is to be applied to connections of floors/hopper
transverse webs to the side girder in way of hopper corner, and to
connections of side girder to hopper/inner bottom plating. Definition of
full and partial penetration welding and their required extent are given
in Ch 12, Sec 3. In order to improve the fatigue strength, weld
enlargement and grinding are applicable to full and partial penetration
welds with a minimum distance of 300 mm from the intersection point
between the radiused knuckle, the floor and the side girder.
|
Table 7 : Design standard G – hopper knuckle connection detail, radiused type,
bulk carrier
Connections of floors in
double bottom tanks to hopper tanks Hopper corner connections employing
radiused knuckle between inner bottom and hopper sloping plating
|
Critical areas
|
Design standard G
|
|
|
Critical locations
|
|
|
Intermediate bracket arrangement
(Section B-B). Two intermediate brackets at both sides of
floor/transverse web.
|
Note 1: Distance from side girder to centre of knuckle is to be as
small as practicable, but is not to exceed 50 mm.
Note 2: The knuckle radius is not to be less than 4.5
tas-built or 100 mm, whichever is the
greater, in cases where tas-built is the as-built
thickness of the knuckle part.
Note 3: Additional transverse brackets on both side of transverse
floor/hopper connection.
Note 4: Transverse brackets may be omitted if it can be demonstrated
that the girder provides sufficient support at the knuckle line,
i.e. that fatigue requirements according to Ch 9, Sec 5 and local
strength analysis requirements according to Ch 7, Sec 3 are
fulfilled.
|
Critical location
|
Side girder connections to inner bottom plating in way of floors.
Floor and hopper transverse web connections to inner bottom plating and
hopper sloping plate, respectively, and to side girder in way of hopper
corners.
|
Detail design standard
|
Elimination of scallops in way of hopper/girder connection.
Ballast holds: Intermediate brackets fitted at approximately 0.5
floor space from floor/hopper web.
Dry holds: Intermediate brackets fitted at 0.5 floor space from
floor/hopper web if floor spacing is equal to or greater than 2.5
m.
|
Building tolerances
|
The nominal distance between the centres of thickness of the two
abutting members (e.g. floor and hopper web plate and additional
supporting brackets) should not exceed 1/3 of the as-built thickness of
the side girder.
|
Welding requirements
|
Full penetration welding is to be applied to connections of floors to
hopper /inner bottom plating in way of radiused hopper knuckle. Partial
penetration welding is to be applied to connections of floors/hopper
transverse webs to side girder in way of hopper corners, to connections
of side girder to hopper /inner bottom plating. Definition of full and
partial penetration welding and their required extent are given in Ch
12, Sec 3.
|
Table 8 : Design standard H – upper hopper knuckle connection detail, radiused
type, oil tankers and double side bulk carrier
Connections of transverse
webs in double side tanks to hopper tanks Hopper corner connections
employing radiused knuckle between side longitudinal bulkhead and hopper
sloping plating
|
Critical areas
|
Design standard H
|
|
|
Critical locations
|
|
Note 1: Distance from side stringer to centre of knuckle is to be as
small as practicable, but is not to exceed 50 mm.
Note 2: The knuckle radius is not to be less than 4.5
tas-built or 100 mm, whichever is the
greater, where tas-built is the as-built thickness
of the knuckle part , according to Ch 12 Sec 1 [3] & [4]
Note 3: Additional transverse brackets offset at a suitable distance
on either side of transverse floor/hopper connection.
Note 4: Additional longitudinal bracket on the side of sloping plate.
Note 5: Longitudinal and/or transverse brackets may be omitted if it
can be demonstrated that the girder provides sufficient support at
the knuckle line, i.e. that fatigue requirements according to Ch 9,
Sec 5 and local strength analysis requirements according to Ch 7,
Sec 3 are fulfilled.
|
Critical location
|
Side stringer connections to side longitudinal bulkhead in way of
transverse webs. Double side tank transverse web and hopper transverse
web connections to side longitudinal bulkhead and to side stringers in
way of hopper corners.
|
Detail design standard
|
Elimination of scallops in way of hopper corners, closer knuckle
distance from side stringers.
Additional longitudinal/transverse brackets to reduce peak and range
of resultant stresses arising from cyclic external hydrodynamic
pressure and cargo inertia pressure.
|
Building tolerances
|
The nominal distance between the centres of thickness of the two
abutting members should not exceed 1/3 of the as-built thickness of the
side stringer.
|
Welding requirements
|
Partial penetration welding is applied to connection of side
stringers to side longitudinal bulkhead, connection of double side tank
transverse webs to side longitudinal bulkhead and to side stringers,
connection of hopper transverse webs to sloped side longitudinal
bulkhead and to side stringers in way of hopper corners. Small scallops
of suitable shape, which are to be closed by welding after completion of
the continuous welding of side stringers to longitudinal bulkhead, are
to be provided where scallops are eliminated. Definition of full and
partial penetration welding and their required extent are given in Ch
12, Sec 3.
|
|