5.1 The applicant should provide as a minimum
the ship electric balance load analysis.
5.2 Such information may contain shipbuilders'
confidential information. Therefore, after the validation, the validator
should return all or part of such information to the applicant at
the applicant's request.
5.3 A special EEDI condition during sea trials
may be needed and defined for each vessel and included into the sea
trial schedule. For this condition a special column should be inserted
into the EPT.