A line drawing of the inert gas system showing the positions
                           of the inert gas pipework from the boiler or gas generator uptakes
                           to each cargo tank and slop tank; gas scrubber; scrubber cooling water
                           pump and pipework up to the effluent discharge overboard; blowers
                           including the suction and discharge valves; recirculation or other
                           arrangements to stabilize the inert gas plant operation; fresh air
                           inlets; automatic gas pressure regulating stop valve; deck water seal
                           and water supply, heating and overflow arrangements; deck nonreturn
                           stop valve; water traps in any supply, vent, drain and sensing pipework;
                           cargo tank isolation arrangement; purge pipes/vents; pressure/vacuum
                           valves on tanks; pressure/vacuum breakers on the inert gas main; permanent
                           recorders and instruments and the take-off points for their use, arrangements
                           for using portable instruments, complete and partial wash bulkheads,
                           mast risers, mast riser isolating valves; high velocity vents; manual
                           and remote controls.