6.1
Bonding procedure qualification
6.1.1 The bonding procedure specification and
qualification test should be defined in accordance with recognized
standards.
6.1.2 The bonding procedures should be fully documented
before work commences to ensure the properties of the bond are acceptable.
6.1.3 The following parameters should be considered
when developing a bonding procedure specification:
-
.1 surface preparation;
-
.2 materials storage and handling prior to installation;
-
.3 covering-time;
-
.4 open-time;
-
.5 mixing ratio, deposited quantity;
-
.6 environmental parameters (temperature, humidity);
and
-
.7 curing pressure, temperature and time.
6.1.4 Additional requirements may be included
as necessary to ensure acceptable results.
6.1.5 The bonding procedures specification should
be validated by an appropriate procedure qualification testing programme.
6.2
Personnel qualifications
6.2.1 Personnel involved in bonding processes
should be trained and qualified to recognized standards.
6.2.2 Regular tests should be made to ensure the
continued performance of people carrying out bonding operations to
ensure a consistent quality of bonding.