5.3.1 For the validity to be renewed for a further three years, the Surveyors
should undertake a periodic inspection in accordance with Ch 1 Procedure 1-1 -
Periodic Inspection of Approved Works in MQPS Book B. To ensure continuity,
this should be carried out within six months prior to the approval expiry date.
5.3.2 It is a Rule requirement that during material surveys the works will be subject to
regular visits to confirm continued compliance with the original approval. The
frequency of visits will depend on the frequency of material surveys. Records of
these visits will be kept by the Surveyors.
5.3.3 Manufacturers that have not produced products under LR survey during the approval
period must either conduct new approval tests (according to Ch 3 procedure 3-2, 5
Approval test programme and Ch 3 procedure 3-2, 6 Specific approval test
results in MQPS Book C) or contact LR to agree on any additional
requirements to continue approval.
5.3.4 Where a manufacturer physically moves the location of an approved works
from the approved location to a new site, the manufacturer will be required to
follow the initial approval process in full unless they can present a satisfactory
case to LR that this is not required.