Section 2 Installation, survey and commissioning testing location
Clasification Society 2024 - Version 9.40
Clasifications Register Guidance Information - Guidance on Ballast Water Management System Commissioning Testing, December 2020 - Chapter 1 Guidance on Ballast Water Management System Commissioning Testing - Section 2 Installation, survey and commissioning testing location

Section 2 Installation, survey and commissioning testing location

2.1 System installation, survey and commissioning

2.1.1 The ideal scenario is that installation, survey and commissioning can be completed in the same location within a similar time frame. This would result in the issuance of an International Ballast Water Management Certificate. However, this may not always be possible. For example, the system may have System Design Limitations or longer holding time requirements than the ship’s schedule permits.

2.2 System installed but not surveyed and commissioned

2.2.1 For situations where the BWMS has been installed into the vessel but not surveyed and commissioned. The installation survey has to be conducted prior to commissioning testing; the shipowners should demonstrate the operation of the BWMS. Commissioning testing has to be completed to obtain an International Ballast Water Management Certificate.

2.3 System installed and surveyed and commissioning testing is started at the same location but needs to be finished in another location

2.3.1 The situation where the BWMS has been installed and surveyed in one location, and commissioning testing commences in the same location. However, because of the hold time limitation of the system, and/or the vessel’s sailing schedule, for example, the discharge sampling cannot take place at the same location and needs to be carried out in a different location.

2.3.2 In such circumstances, the ship may require short term BWM Convention certification, subject to consideration by the Flag Administration.

2.4 System installed and surveyed but commissioning testing cannot be conducted at the same location

2.4.1 The situation where the BWMS has been installed and surveyed in one location, but owing to the System Design Limitations, the BWMS is not compatible with the ambient water and commissioning testing needs to be done in a different location.

2.4.2 In such circumstances, the ship may require short term BWM Convention certification, subject to consideration by the Flag Administration.


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.