3.1.1 Submarine Assurance planning is to establish and document the scope of the Submarine
Assurance activities required to be carried out by LR.
3.1.2 The submarine Owner is to have an appropriate Submarine Safety Management System in
place.
3.1.3 The submarine Owner, designer, builder or maintenance organisation is to have an
appropriate Submarine Safety Assurance System in place for the lifecycle phase or
phases for which Submarine Assurance is required.
3.1.4 The submarine Owner, designer, builder or maintenance organisation is to have an
appropriate Quality Management System in place covering the design, construction or
maintenance of submarines as appropriate.
3.1.5 The Quality Management System is to be in accordance with a recognised and acceptable
international, national or sector standard.
3.1.6 The submarine designer is to have an appropriate Systems Engineering Management
System in place for the design of the submarine where Submarine Assurance is
required for the design phase of the submarine lifecycle.
3.1.7 The Systems Engineering Management System is to be in accordance with a recognised
and acceptable international, national or sector standard.
3.1.8 The assurance activities required to be carried out by LR are to be established based
on the Submarine Safety Assurance System in consultation with the submarine Owner,
designer, builder or maintenance organisation as appropriate.
3.1.9 A Submarine Assurance Plan will be prepared by LR in consultation with the submarine
designer, builder or maintenance organisation.
3.1.10 The plan will define the roles and responsibilities of the entities involved.
3.1.11 The plan will define the scope of activity to be carried out by LR in terms of the
Submarine Assurance Framework Goals, Functional Objectives and Performance
Requirements within scope, in terms of the submarine systems within scope and in
terms of submarine lifecycle phases within scope.
3.1.12 The plan will describe the assurance activities to be carried out by LR in accordance
with the submarine systems or in accordance with the submarine Work Breakdown
Structure.
3.1.13 The plan is to be agreed by the submarine Owner and Naval Administration.