Construction stage
|
|
Inspection items
|
Primary surface preparation
|
1
|
The surface temperature of steel, the
relative humidity and the dew point should be measured and recorded before the
blasting process starts and at times of sudden changes in weather.
|
|
2
|
The surface of steel plates should be
tested for soluble salt checked for oil, grease and other
contamination.
|
|
3
|
The cleanliness of the steel surface
should be monitored in the shop primer application process.
|
|
4
|
The shop primer material should be
confirmed to meet the requirements of 2.3 of table 1.
|
Thickness
|
|
If compatibility with the main coating
system has been declared, then the thickness and curing of the zinc silicate
shop primer should be confirmed to conform to the specified values.
|
Block assembly
|
1
|
After completing construction of the
block and before secondary surface preparation starts, a visual inspection for
steel surface treatment including edge treatment should be carried out.
|
|
|
Any oil, grease or other visible
contamination should be removed.
|
|
2
|
After blasting/grinding/cleaning and
prior to coating, a visual inspection of the prepared surface should be carried
out.
|
|
|
On completion of blasting and cleaning
and prior to the application of the first coat of the system, the steel surface
should be tested for levels of remaining soluble salts in at least one location
per block.
|
|
3
|
The surface temperature, the relative
humidity and the dew point should be monitored and recorded during the coating
application and curing.
|
|
4
|
Inspection should be performed of the
steps in the coating application process mentioned in table 1.
|
|
5
|
DFT measurements should be taken to
prove that the coating has been applied to the thickness as specified and
outlined in annex 3.
|
Erection
|
1
|
Visual inspection for steel surface
condition, surface preparation and verification of conformance to other
requirements in table 1, and the agreed specification should be
performed.
|
|
2
|
The surface temperature, the relative
humidity and the dew point should be measured and recorded before coating
starts and regularly during the coating process.
|
|
3
|
Inspection should be performed of the
steps in the coating application process mentioned in table 1.
|